After working for 8 days, Hari Ram finds that only 1/3 rd of the work has been done. He employs Satya who is 60% as efficient as Hari Ram. How many days more would Satya take to complete the work ?

Correct Answer: 26 2/3 days

Explanation:

1/3 ---- 8


1 -------?
Hari can do total work in = 24 days


As satya is 60% efficient as Hari, then


Satya = 1/24 x 60/100 = 1/40


=> Satya can do total work in 40 days


1 ----- 40


2/3 ---- ? => 26 2/3 days.