Home » Aptitude » Time and Work

A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?

Correct Answer: 19

← Previous Question Next Question→

More Questions from Time and Work

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion