Difficulty: Easy
Correct Answer: 40/9 days
Explanation:
Introduction / Context:
Here, you are given the number of days two workers A and B take individually to complete a job. The question asks how long they will take to finish the job when they work together. This is a standard time and work problem that uses basic rate addition.
Given Data / Assumptions:
Concept / Approach:
If a worker can finish a job in T days, the worker's daily rate is 1/T of the job per day. When multiple workers cooperate, their individual rates add up. We thus find the combined rate of A and B and then take the reciprocal of that combined rate to find the number of days required to finish the job.
Step-by-Step Solution:
Let total work = 1 unit.
Daily rate of A = 1/8 of the job per day.
Daily rate of B = 1/10 of the job per day.
Combined daily rate = 1/8 + 1/10.
Take the LCM of 8 and 10, which is 40.
Convert fractions: 1/8 = 5/40 and 1/10 = 4/40.
Combined rate = 5/40 + 4/40 = 9/40 of the job per day.
Time taken together = total work / combined rate = 1 / (9/40) = 40/9 days.
Verification / Alternative check:
If they complete 9/40 of the job per day, then over 40/9 days they would do (9/40)*(40/9) = 1 job, which is correct. Also, note that A alone needs 8 days and B alone needs 10 days, so the combined time must be less than 8 days but reasonably close. 40/9 is approximately 4.44 days, which fits within this expectation and confirms the plausibility of the result.
Why Other Options Are Wrong:
Option 33/8 days is approximately 4.125 days, which implies a slightly higher combined rate than 9/40 and does not match the correct sum of rates.
Option 41/10 days is 4.1 days, which similarly conflicts with the combined rate computed by proper fraction addition.
Option 42/11 days is around 3.82 days and is too small given the individual times of 8 and 10 days.
Option 4 days would require a combined rate of 1/4 per day, which is larger than 9/40 and not equal to 1/8 + 1/10.
Common Pitfalls:
A common mistake is to average the times 8 and 10 to get 9 days, which is incorrect. Another pitfall is miscalculating the LCM or addition of fractions, leading to a wrong combined rate. Remember to always work with rates 1/T, add them carefully, and then invert the sum to find the total time.
Final Answer:
Thus, A and B working together can complete the work in 40/9 days, so the correct option is 40/9 days.
Discussion & Comments