A can do a job in 10 days. B is 60 percent more efficient than A. In how many days can B alone complete the same job?

Difficulty: Easy

Correct Answer: 6 1/4

Explanation:


Introduction / Context:
Efficiency comparisons translate into rate multipliers. If B is 60 percent more efficient than A, B’s work rate is 1.6 times A’s rate. Time is the reciprocal of rate for one whole job.



Given Data / Assumptions:


  • A time = 10 days ⇒ A rate = 1/10 per day.
  • B efficiency = 160 percent of A.


Concept / Approach:
Multiply A’s rate by 1.6 to get B’s rate, then take the reciprocal to obtain B’s time to finish one job.



Step-by-Step Solution:


B rate = 1.6 * (1/10) = 0.16 per dayB time = 1 / 0.16 = 6.25 days = 6 1/4 days


Verification / Alternative check:
If A does 1 unit in 10 days, in 6.25 days A would do 0.625 units. Since B is 1.6 times as fast, B’s output in 6.25 days is 1 unit, confirming the calculation.



Why Other Options Are Wrong:
6 and 6 2/3 arise from rounding or misinterpreting 60 percent more as 60 percent of A; 8 days assumes B is slower than reality; 5 days overestimates B’s efficiency.



Common Pitfalls:
Confusing 60 percent more with 60 percent of; converting 0.25 to fractional days incorrectly; mixing time and rate comparisons directly.



Final Answer:
6 1/4

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion