CuriousTab
Search
CuriousTab
Home
Aptitude
Computer
C Programming
C# Programming
C++ Programming
Database
Java Programming
Networking
Engineering
Biochemical Engineering
Biochemistry
Biotechnology
Chemical Engineering
Civil Engineering
Computer Science
Digital Electronics
Electrical Engineering
Electronics
Electronics and Communication Engineering
Mechanical Engineering
Microbiology
Technical Drawing
GK
Current Affairs
General Knowledge
Reasoning
Data Interpretation
Logical Reasoning
Non Verbal Reasoning
Verbal Ability
Verbal Reasoning
Exams
AIEEE
Bank Exams
CAT
GATE
IIT JEE
TOEFL
Jobs
Analyst
Bank PO
Database Administrator
IT Trainer
Network Engineer
Project Manager
Software Architect
Water Supply Engineering problems
1. The transitional middle portion of a logistic curve follows
Options
A. a geometric growth
B. a logarithmic growth
C. a first over curve
D. a constant rate.
Show Answer
Scratch Pad
Discuss
Correct Answer: a constant rate.
2. Most satisfactory formula for an estimate of fire demand
Q
for a city of population
P
in thousands for Indian conditions, is
Options
A.
B.
Q
= 1640
P
(1 - 0.01
P
)
C.
Q
= 3180
P
D. none of these.
Show Answer
Scratch Pad
Discuss
Correct Answer:
Q
= 3180
P
3. Water supply system includes
Options
A. digging a well for water
B. construction of dams
C. construction of canals
D. entire arrangement from source to distribution.
Show Answer
Scratch Pad
Discuss
Correct Answer: entire arrangement from source to distribution.
4. Biochemical Oxygen Demand (B.O.D.) of safe drinking water must be
Options
A. nil
B. 5
C. 10
D. 15
E. 20
Show Answer
Scratch Pad
Discuss
Correct Answer: nil
5. Turbidity of raw water is a measure of
Options
A. suspended solids
B. acidity of water
C. B.O.D.
D. none of these.
Show Answer
Scratch Pad
Discuss
Correct Answer: suspended solids
6. The fire demand of a city may be worked out by
Options
A. Kuichling's formula
B. Freeman formula
C. Under Writers formula
D. Bustan's formula
E. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
7. Most commonly used pump for lifting water in water supply mains, is
Options
A. axialflow pump
B. reciprocating pump
C. rotary type pump
D. centrifugal pumps
E. none of these.
Show Answer
Scratch Pad
Discuss
Correct Answer: axialflow pump
8. Surge tanks are used
Options
A. for storage water
B. to increase the velocity in a pipeline
C. as overflow valves
D. to guard against water hammer.
Show Answer
Scratch Pad
Discuss
Correct Answer: to guard against water hammer.
9. Asbestos pipes are
Options
A. light in weight and easy to transport
B. highly resistant to corrosion
C. high flexible to accommodate deflection upto 12°
D. very much smooth and hydraulically efficient
E. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: all the above.
10. Hard water for public water supply is discarded because
Options
A. it consumes more soap
B. it contains lot of turbidity
C. it contains pathogenic bacterias
D. it possesses bad taste and odour
E. none of these.
Show Answer
Scratch Pad
Discuss
Correct Answer: it consumes more soap
First
5
6
7
...
21
..
35
36
Last
More in Civil Engineering:
Advanced Surveying
Airport Engineering
Applied Mechanics
Building Construction
Building Materials
Concrete Technology
Construction Management
Docks and Harbours
Elements of Remote Sensing
Engineering Economy
Estimating and Costing
GATE Exam Questions
Highway Engineering
Hydraulics
Irrigation
Railways
RCC Structures Design
SI Units
Soil Mechanics and Foundation Engineering
Steel Structure Design
Strength of Materials
Structural Design Specifications
Surveying
Theory of Structures
Tunnelling
UPSC Civil Service Exam Questions
Waste Water Engineering
Water Resources Engineering
Water Supply Engineering