CuriousTab
Search
CuriousTab
Home
Aptitude
Computer
C Programming
C# Programming
C++ Programming
Database
Java Programming
Networking
Engineering
Biochemical Engineering
Biochemistry
Biotechnology
Chemical Engineering
Civil Engineering
Computer Science
Digital Electronics
Electrical Engineering
Electronics
Electronics and Communication Engineering
Mechanical Engineering
Microbiology
Technical Drawing
GK
Current Affairs
General Knowledge
Reasoning
Data Interpretation
Logical Reasoning
Non Verbal Reasoning
Verbal Ability
Verbal Reasoning
Exams
AIEEE
Bank Exams
CAT
GATE
IIT JEE
TOEFL
Jobs
Analyst
Bank PO
Database Administrator
IT Trainer
Network Engineer
Project Manager
Software Architect
Waste Water Engineering problems
1. If the depletion of oxygen is found to be 2.5 mg/litre after incubating 2.5 ml of sewage diluted to 250 ml for 5 days at 20°C, B.O.D. of the sewage is
Options
A. 50 mg/l
B. 100 mg/l
C. 150 mg/l
D. 200 mg/l
E. 250 mg/l.
Show Answer
Scratch Pad
Discuss
Correct Answer: 250 mg/l.
2. It is customary to design a sewer for D.W.F. on the basis of
Options
A. average demand
B. twice the average demand
C. thrice the average demand
D. four times the average demand.
Show Answer
Scratch Pad
Discuss
Correct Answer: thrice the average demand
3. The detention period for plain sedimentation water tanks, is usually
Options
A. 4 to 8 hours
B. 8 to 16 hours
C. 16 to 24 hours
D. 24 to 36 hours.
Show Answer
Scratch Pad
Discuss
Correct Answer: 4 to 8 hours
4. Sewer ventilating columns are generally placed at
Options
A. distances 150 m to 300 m
B. upper ends of branch sewers
C. every change in the size of sewers
D. all the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: all the above.
5. In case of Imhoff tanks,
Options
A. the shape is rectangular
B. detention period is 2 hours
C. the velocity of flow is restricted to 0.30 m/minute
D. surface loading is limited to 30, 000 litres/m of plan area per day
E. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
6. Pick up the correct statement from the following :
Options
A. The materials separated by screens, is called screenings
B. The screenings are disposed off either by burning or by burial or by dumping
C. The process of burning the screenings, is called incineration
D. The process of burning the screenings, is known as compositing
E. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
7. In sewers the highest non-scouring velocity is achieved in
Options
A. glazed bricks sewers
B. cast iron sewers
C. cement concrete sewers
D. stone ware sewers.
Show Answer
Scratch Pad
Discuss
Correct Answer: glazed bricks sewers
8. The standard B.O.D. of water is taken for
Options
A. 1 day
B. 2 days
C. 3 days
D. 5 days
E. 10 days.
Show Answer
Scratch Pad
Discuss
Correct Answer: 5 days
9. The ratio of the diameter of a circular section and the side of a square section hydraulically equivalent, is
Options
A. 1.095
B. 1.085
C. 1.075
D. 1.065
Show Answer
Scratch Pad
Discuss
Correct Answer: 1.095
10. The digested sludge from septic tanks, is removed after a maximum period of
Options
A. 3 years
B. 3.5 years
C. 4 years
D. 5 years.
Show Answer
Scratch Pad
Discuss
Correct Answer: 3 years
First
8
9
10
...
20
..
31
32
Last
More in Civil Engineering:
Advanced Surveying
Airport Engineering
Applied Mechanics
Building Construction
Building Materials
Concrete Technology
Construction Management
Docks and Harbours
Elements of Remote Sensing
Engineering Economy
Estimating and Costing
GATE Exam Questions
Highway Engineering
Hydraulics
Irrigation
Railways
RCC Structures Design
SI Units
Soil Mechanics and Foundation Engineering
Steel Structure Design
Strength of Materials
Structural Design Specifications
Surveying
Theory of Structures
Tunnelling
UPSC Civil Service Exam Questions
Waste Water Engineering
Water Resources Engineering
Water Supply Engineering