logo

CuriousTab

CuriousTab

Engineering Economy problems


  • 1. The project contractor relies on the cost of the estimate :

  • Options
  • A. for submission of a competitive bid for a lumpsum contract
  • B. for a unit price contract
  • C. for preparation of a definitive estimate to help negotiate contract.
  • D. All of these
  • Discuss
  • 2. Pick up the correct reason for making conceptual (or preliminary) estimate from the following:

  • Options
  • A. To have a check on a definitive cost estimate.
  • B. To check qoutations from contractors and/or sub contractors.
  • C. To compute target estimate for the owner while drawings and specifications are in initial stage.
  • D. All of these.
  • Discuss
  • 3. Current assests less inventories divided by current liabilities is known as

  • Options
  • A. Liquidity ratio
  • B. Current ratio
  • C. Acid-Test (or Quick) ratio
  • D. Debts ratio
  • Discuss
  • 4. The financial analysis helps to judge:

  • Options
  • A. The operational efficiency of the firm
  • B. The financial position of the firm.
  • C. Both (a) and (b)
  • D. Neither (a) nor (b)
  • Discuss
  • 5. Pick up the element of the cost from the following:

  • Options
  • A. direct material
  • B. direct labour
  • C. Over head
  • D. All of these
  • Discuss
  • 6. Refer to the cash flow diagram of uniform gradient in a cash flow (in the given figure), the gradient is :
    Civil Engineering Engineering Economy: Refer to the cash flow diagram of uniform gradient in a cash flow (in the given figure), the gradien

  • Options
  • A. Rs 10000 per year
  • B. Rs 15000 per year
  • C. Rs 20000 per year
  • D. Rs 25000 per year
  • Discuss
  • 7. Pick up the correct statement from the following:

  • Options
  • A. The ability of a company to meet obligations which are likely to mature in short term, is called liquidity.
  • B. The liquidity ratio may be defined as a relationship of current liabilities and current assests and advances.
  • C. The liquidity ratios are used to indicate the financial position of the firm.
  • D. All of these
  • Discuss
  • 8. If P is principal amount, i is the rate of interest and n is the number of periods in years, then the interest factor is :

  • Options
  • A. (1 + ni)
  • B. (ni - 1)
  • C. ni
  • D. None of these
  • Discuss
  • 9. Pick up the correct statement from the following:

  • Options
  • A. An annuity is a series of equal payments occurring at equal period of time.
  • B. Annuity is called an equal payment or uniform payment series.
  • C. An annuity may have periods of time of any length but should always be of equal length.
  • D. All the above.
  • Discuss
  • 10. The key to profitable operation for project cost control, is :

  • Options
  • A. To keep the project cost equal to original cost estimate.
  • B. To keep the project cost equal to subsequent construction budget.
  • C. To keep the project cost within the cost budget and knowing when and where job costs are deviating.
  • D. None of these
  • Discuss

First 2 3 4 5 6 7 8