logo

CuriousTab

CuriousTab

Building Construction problems


  • 1. Pick up the correct statement from the following:

  • Options
  • A. Louvered door is generally provided in bath rooms
  • B. Flush door is generally provided in dinning room
  • C. Revolving door is generally provided in cinema halls
  • D. Sliding door is generally provided in show rooms
  • E. All the above.
  • Discuss
  • 2. A projecting piece usually provided to support a truss, is

  • Options
  • A. cornice
  • B. coping
  • C. frieze
  • D. lintal.
  • Discuss
  • 3. To ensure that supporting area of an offset footing of a boundary wall is fully compressive, the C.G. of load must act

  • Options
  • A. at the centre of the base
  • B. within the middle third of the base
  • C. within the middle fifth of the base
  • D. neither (a), (b) nor (c).
  • Discuss
  • 4. The raft slab is projected beyond the outer walls of the structure by

  • Options
  • A. 5 to 10 cm
  • B. 15 to 20 cm
  • C. 25 to 30 cm
  • D. 30 to 45 cm
  • E. 60 cm.
  • Discuss
  • 5. The form work from the underside of slabs, can be removed only after

  • Options
  • A. 1 day
  • B. 4 days
  • C. 7 days
  • D. 14 days.
  • Discuss
  • 6. Pick up the incorrect statement from the following :

  • Options
  • A. Cement is added to lime mortar to increase its hydraulic properties only
  • B. Lime surkhi mortar is used for pointing the walls
  • C. Lime should be slaked before preparing lime mortar
  • D. High early strength concrete is generally used in cold weather.
  • Discuss
  • 7. During percussion drilling

  • Options
  • A. ground water observations are hindered due to entry of the slurry in the soil below the bottom of the hole
  • B. caving or mixing of strata are caused in soft soils or cohesionless soils
  • C. the soil to a considerable depth below the bottom of the hole gets disturbed
  • D. all the above.
  • Discuss
  • 8. If (?) is the angle of repose of soil of weight w kg/m3, the horizontal pressure p at a depth of h metres per metre length of wall, is

  • Options
  • A.
  • B.
  • C.
  • D.
  • Discuss
  • 9. The single stage well point system of dewatering an excavation can be used if the depth of excavation does not exceed

  • Options
  • A. 5 m
  • B. 10 m
  • C. 15 m
  • D. 20 m
  • E. 25 m.
  • Discuss
  • 10. For providing a raft foundation, the following activities are involved

    1. ramming the foundation bed
    2. excavation of the soil upto required depth
    3. laying the reinforcement over the foundation bed
    4. curing the cement concrete placed over reinforcement
    5. pouring the cement concrete over the reinforcement.

    The correct sequence is

  • Options
  • A. 1, 2, 3, 4, 5
  • B. 5, 4, 3, 2, 1
  • C. 2, 1, 3, 5, 4
  • D. 3, 2, 5, 1, 4.
  • Discuss

First 5 6 7 ... 14 .. 22 23 Last