6th March 2005 = Monday.
Then, 6th March 2004 = Monday - 1 days = Sunday.
(2004 is a leap year but it does not cross 29th February of 2004, so only 1 is taken as odd day).
6th March 2004 = Sunday
7th March 2004 = Monday.
4th observation i.e., 8 is the median.
47/10000 = .0047
.02 =(2/100) x 100% =2%
Let N / 11 = 233
Then, N = 233 x 11 = 2563
? Missing digit is 5.
121012 = 12 x 10084 + 4
? remainder = 4
We have the important relation, More work, More time (days)
? A piece of work can be done in 6 days.
? Three times of work of same type can be done in 6 x 3
= 18 days
? = 750.0003 ÷ 19.999
? ? ? 750 ÷ 20
? ? ? 375 ? 38
Comments
There are no comments.Copyright ©CuriousTab. All rights reserved.