logo

CuriousTab

CuriousTab

Discussion


Home Aptitude Time and Work Comments

  • Question
  • If 14 men and 12 boys can finish work in 4 days, while 8 men and 16 boys can finish the same work in 5 days. Compare the 1 days work of 1 man and 1 boy.


  • Options
  • A. 2
  • B. 11/2
  • C. 1/2
  • D. 3

  • Correct Answer


  • Explanation

    Here, a1 = 14, b1 = 12, p = 4, a2 = 8, b2 = 16 and q = 5
    One days work of 1 man/One days of 1 boy
    = (qb2 - pb1) / ( pa1 - qa2)
    = [5 x 16 - 4 x 12] / [ 4 x 14 - 5 x 8]
    = (80 - 48) / (56 - 40)
    = 32/16
    = 2


  • Time and Work problems


    Search Results


    • 1. 
      A contract is to be complete in 50 days and 105 men were set to work, each working 8 h a day. After 25 days, 2/5th of the work is finished. How many additional men be employed, so that the work may be completed on time, each man now working 9 h a day?

    • Options
    • A. 34
    • B. 36
    • C. 35
    • D. 37
    • Discuss
    • 2. 
      5 men started working to complete a work in 15 days. After 5 days, 10 women are accompanied by to them to complete the work in next 5 days. If the work is to be done by women only, when could the work be over, if 10 women have started it?

    • Options
    • A. 10 days
    • B. 18 days
    • C. 15 days
    • D. 12 days
    • Discuss
    • 3. 
      10 men and 8 women together can complete a work in 5 days. Work done by one women in day is equal to half the work done by man in 1 day. How many days will it take for 4 men and 6 women to complete that work?

    • Options
    • A. 12 days
    • B. 10 days
    • C. 82/3
    • D. 43/4 days
    • Discuss
    • 4. 
      A takes twice as much time as B, and C take thrice as much time as B to finish a work. Working together, they can finish the work in 12 days. Find the number of days needed for A to do the work alone.

    • Options
    • A. 20
    • B. 22
    • C. 33
    • D. 44
    • Discuss
    • 5. 
      16 children and 24 men complete a certain work for 18 days. If each child takes twice the time taken by a man to finish the work in how many days will 24 men finish the same work?

    • Options
    • A. 12 days
    • B. 24 days
    • C. 36 days
    • D. 48 dyas
    • Discuss
    • 6. 
      In a factory, there are equal number of women and children. Women work for 6 h a days and children for 4 h a day. During festival time, the work load goes up by 50%. The government rule does not allow children to work for more then 6 h a day. If they are equally efficient and the extra work is done by women, then extra hours of work put in by women everyday are?

    • Options
    • A. 5
    • B. 3
    • C. 4
    • D. 9
    • Discuss
    • 7. 
      3 women and 18 children together take 2 days to complete a piece of work. How many days will 9 children alone take to complete the piece of work, if 6 women alone can complete the piece of work in 3 days?

    • Options
    • A. 9
    • B. 7
    • C. 5
    • D. 6
    • Discuss
    • 8. 
      A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharge now, so that the work finish in time?

    • Options
    • A. 40
    • B. 50
    • C. 48
    • D. 56
    • Discuss
    • 9. 
      A contract is to be complete in 92 days and 234 men were set to work, each working 16 h a days. After 66 days, 4/7 of the work is completed. How many addition men may be employed, so that the work may be completed in time, each man now working 18 h a day?

    • Options
    • A. 162
    • B. 234
    • C. 262
    • D. 81
    • Discuss
    • 10. 
      A, B and C can do a piece of work in 16, 32 and 48 days, respectively. They all begin together. A work continuously till it is finished, C leaves the work 2 days before its completion and B leaves the work in 1 days before its complete. In what time is the work finished?

    • Options
    • A. 10 days
    • B. 20 days
    • C. 15 days
    • D. 30 days
    • Discuss


    Comments

    There are no comments.

Enter a new Comment