logo

CuriousTab

CuriousTab

Discussion


Home Aptitude Time and Work Comments

  • Question
  • A, Band C can do a piece of work individually in 8, 12 and 15 days, respectively. A and B start working but A quits after working for 2 days. After this, C joins B till the completion of work. In how many days will the work be completed?


  • Options
  • A. 58/9 days
  • B. 46/7 days
  • C. 67/13 days
  • D. 33/4 days

  • Correct Answer
  • 58/9 days 

    Explanation

    Work done by A and B in 1 day
    = (1/8) + (1/12) = 5/24
    2 day's work of A and B = 10/24
    After 2 day's A left the work
    ? Remaining work = 1 - (10/24) = 14/24
    One day work of B and C together = (1/12) + (1/15) = 9/60
    So, the number of days required by B and C to finish work
    = (14/24) / (9/60) = (14/24) x (60/9) = 35/9
    ? Total days to complete the work = 2 + (35/9) = 53/9 = 58/9 days


  • Time and Work problems


    Search Results


    • 1. 
      90 men are engaged to do piece of work in 40 days but it is found that in 25 days, 2/3 work is complete. How many men should be allowed to go off, so that the work finished in time?

    • Options
    • A. 10
    • B. 15
    • C. 20
    • D. 25
    • Discuss
    • 2. 
      20 workers working for 5 h per day complete a work in 10 days. If 25 workers are employed to work 10 h per days, what is the time required to complete the work?

    • Options
    • A. 4 days
    • B. 5 days
    • C. 6 days
    • D. 8 days
    • Discuss
    • 3. 
      A and B can complete a job in the 24 days working together. A alone can complete it in 32 days. Both of them worked together for 8 days and then A left. The number of days B will take to complete the remaining job is

    • Options
    • A. 16
    • B. 32
    • C. 64
    • D. 128
    • Discuss
    • 4. 
      A and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after 2 more days, B alone could do the work in how many days?

    • Options
    • A. 5
    • B. 6
    • C. 7
    • D. 10
    • Discuss
    • 5. 
      Ajay can do a piece of work in 25 days and Sanjay can finish it in 20 days. They work together for 5 days and then Ajay goes away. In how many days will Sanjay finish the remaining work?

    • Options
    • A. 11 days
    • B. 12 days
    • C. 14 days
    • D. None of these
    • Discuss
    • 6. 
      A and B can do a piece of work in 9 days and 18 days, respectively. As they were ill, they could do 90% and 72% of their efficiency, respectively. How many days will they take to complete the work together?

    • Options
    • A. 71/7
    • B. 8
    • C. 5
    • D. 121/2
    • Discuss
    • 7. 
      36 workmen are employed to finish a certain work in 48 days. But it is found that in 24 days only 2/5 work is done. How many more men must be employed to finish the work in this?

    • Options
    • A. 16
    • B. 18
    • C. 20
    • D. 22
    • Discuss
    • 8. 
      It is given that 16 men working 18 h a day can build a wall 36 m long, 4 m broad and 24 m high in 20 days. How many men will be required to build a wall 64 m long, 6 m broad and 18 m high working 12 h a day in 16 days?

    • Options
    • A. 60
    • B. 20
    • C. 30
    • D. 35
    • Discuss
    • 9. 
      A men can do a piece of work in 5 days. With the help of his friend, he can do the same work in 3 days. In how many days can his friend complete the work?

    • Options
    • A. 6 days
    • B. 61/2 days
    • C. 7 days
    • D. 71/2
    • Discuss
    • 10. 
      A and B each working alone can do a work in 15 days and 25 days, respectively. They started the work together but B left after some time and A finished the remaining work in 7 days. After how many days from the start did B leave?

    • Options
    • A. 3
    • B. 5
    • C. 7
    • D. 9
    • Discuss


    Comments

    There are no comments.

Enter a new Comment