logo

CuriousTab

CuriousTab

Discussion


Home Aptitude Time and Work Comments

  • Question
  • A and B can complete a work in 8 days. working together. B alone can do it in 12 days. After working for 4 days, B left the work. How many days will A take to complete the remaining work?


  • Options
  • A. 16 days
  • B. 18 days
  • C. 20 days
  • D. 22 days

  • Correct Answer
  • 16 days 

    Explanation

    ( A + B) 's 1 days work = 1/8
    B's 1 days work = 1/12
    ? A's 1 day's work = (1/8) - (1/12) = (3 - 2)/24 = 1/24
    ? A can complete the work in 24 days
    Now, B's 4 days work = 4/12 = 1/3
    Remaining work = 1 - 1/3 = 2/3
    As, time taken by A to complete the work is 24 days.
    ? Time taken by A to do 2/3 of the work = 2/3 x 24 = 16 days


  • Time and Work problems


    Search Results


    • 1. 
      Ganesh, Ram and Sohan together can do a work in 16 days. If Ganesh and Ram together can do the same work in 24 days then, how long will take Sohan alone to do the same work?

    • Options
    • A. 42 days
    • B. 24 days
    • C. 36 days
    • D. 48 days
    • Discuss
    • 2. 
      15 men can complete a work in 10 days while 20 boys can complete the same work in 15 days. How many days will 10 men and 10 boys together take to complete the same work?

    • Options
    • A. 10 days
    • B. 8 days
    • C. 12 days
    • D. 9 days
    • Discuss
    • 3. 
      A report of 100 pages is to be typed by three typists. Typist A can type 100 pages in 10 hours. Typist B can type the same pages in 20 hours and typist C in 25 hours. Allthe three typist started typing at 09.00 a.m. At 01.00 p.m. typist A stopped typing. The other two typist finished the job, approximately at what time the report was typed?

    • Options
    • A. 2.40 p.m.
    • B. 5.00 p.m.
    • C. 6.00 p.m.
    • D. 3.40 p.m.
    • Discuss
    • 4. 
      16 men and 12 women together complete a work in 20 days. If 18 women complete the same work in 40 days. Then how many days will be taken by 12 men and 27 women together to complete the same work?

    • Options
    • A. 18 days
    • B. 15 days
    • C. 14 days
    • D. 16 days
    • Discuss
    • 5. 
      Two workers A and B working together completed a job in 5 days. If A worked twice as efficiently as he actually did and B worked 1 / 3 as efficiently as he actually did the work, then they would have completed the work in 3 days. Find the time for A to complete the job alone?

    • Options
    • A. 61/2 days
    • B. 61/4 days
    • C. 63/4 days
    • D. 121/2 days
    • Discuss
    • 6. 
      Ajay can do a piece of work in 25 days and Sanjay can finish it in 20 days. They work together for 5 days and then Ajay goes away. In how many days will Sanjay finish the remaining work?

    • Options
    • A. 11 days
    • B. 12 days
    • C. 14 days
    • D. None of these
    • Discuss
    • 7. 
      A and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after 2 more days, B alone could do the work in how many days?

    • Options
    • A. 5
    • B. 6
    • C. 7
    • D. 10
    • Discuss
    • 8. 
      A and B can complete a job in the 24 days working together. A alone can complete it in 32 days. Both of them worked together for 8 days and then A left. The number of days B will take to complete the remaining job is

    • Options
    • A. 16
    • B. 32
    • C. 64
    • D. 128
    • Discuss
    • 9. 
      20 workers working for 5 h per day complete a work in 10 days. If 25 workers are employed to work 10 h per days, what is the time required to complete the work?

    • Options
    • A. 4 days
    • B. 5 days
    • C. 6 days
    • D. 8 days
    • Discuss
    • 10. 
      90 men are engaged to do piece of work in 40 days but it is found that in 25 days, 2/3 work is complete. How many men should be allowed to go off, so that the work finished in time?

    • Options
    • A. 10
    • B. 15
    • C. 20
    • D. 25
    • Discuss


    Comments

    There are no comments.

Enter a new Comment