logo

CuriousTab

CuriousTab

Discussion


Home Aptitude Time and Work Comments

  • Question
  • Ganesh, Ram and Sohan together can do a work in 16 days. If Ganesh and Ram together can do the same work in 24 days then, how long will take Sohan alone to do the same work?


  • Options
  • A. 42 days
  • B. 24 days
  • C. 36 days
  • D. 48 days

  • Correct Answer
  • 48 days 

    Explanation

    ? Work of (Ganesh, Ram and Sohan) for 1 day = 1/16
    and work of Ganesh and Ram for 1 day = 1/24
    ? Work of Sohan for 1 day = 1/16 - 1/24 = 1/48
    ? Sohan alone will complete the work in = 1/(1/48) days = 48 days.


  • Time and Work problems


    Search Results


    • 1. 
      15 men can complete a work in 10 days while 20 boys can complete the same work in 15 days. How many days will 10 men and 10 boys together take to complete the same work?

    • Options
    • A. 10 days
    • B. 8 days
    • C. 12 days
    • D. 9 days
    • Discuss
    • 2. 
      A report of 100 pages is to be typed by three typists. Typist A can type 100 pages in 10 hours. Typist B can type the same pages in 20 hours and typist C in 25 hours. Allthe three typist started typing at 09.00 a.m. At 01.00 p.m. typist A stopped typing. The other two typist finished the job, approximately at what time the report was typed?

    • Options
    • A. 2.40 p.m.
    • B. 5.00 p.m.
    • C. 6.00 p.m.
    • D. 3.40 p.m.
    • Discuss
    • 3. 
      16 men and 12 women together complete a work in 20 days. If 18 women complete the same work in 40 days. Then how many days will be taken by 12 men and 27 women together to complete the same work?

    • Options
    • A. 18 days
    • B. 15 days
    • C. 14 days
    • D. 16 days
    • Discuss
    • 4. 
      Two workers A and B working together completed a job in 5 days. If A worked twice as efficiently as he actually did and B worked 1 / 3 as efficiently as he actually did the work, then they would have completed the work in 3 days. Find the time for A to complete the job alone?

    • Options
    • A. 61/2 days
    • B. 61/4 days
    • C. 63/4 days
    • D. 121/2 days
    • Discuss
    • 5. 
      A and B can together finish a work in 30 days. They worked for it for 20 days and then B left. the remaining work was done by A alone in 20 more days. A alone can finish the work in?

    • Options
    • A. 48 days
    • B. 50 days
    • C. 54 days
    • D. 60 days
    • Discuss
    • 6. 
      A and B can complete a work in 8 days. working together. B alone can do it in 12 days. After working for 4 days, B left the work. How many days will A take to complete the remaining work?

    • Options
    • A. 16 days
    • B. 18 days
    • C. 20 days
    • D. 22 days
    • Discuss
    • 7. 
      Ajay can do a piece of work in 25 days and Sanjay can finish it in 20 days. They work together for 5 days and then Ajay goes away. In how many days will Sanjay finish the remaining work?

    • Options
    • A. 11 days
    • B. 12 days
    • C. 14 days
    • D. None of these
    • Discuss
    • 8. 
      A and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after 2 more days, B alone could do the work in how many days?

    • Options
    • A. 5
    • B. 6
    • C. 7
    • D. 10
    • Discuss
    • 9. 
      A and B can complete a job in the 24 days working together. A alone can complete it in 32 days. Both of them worked together for 8 days and then A left. The number of days B will take to complete the remaining job is

    • Options
    • A. 16
    • B. 32
    • C. 64
    • D. 128
    • Discuss
    • 10. 
      20 workers working for 5 h per day complete a work in 10 days. If 25 workers are employed to work 10 h per days, what is the time required to complete the work?

    • Options
    • A. 4 days
    • B. 5 days
    • C. 6 days
    • D. 8 days
    • Discuss


    Comments

    There are no comments.

Enter a new Comment