Since, 50 men can do a job in 50 days.
So, work done by 1 man in a day = 1/(50 x 50)
Also, 80 women can do the job in 50 days.
So, work done by 1 women in 1 day = 1/(50 x 80)
Now, work done by 40 men and 48 women in first 10 days
= (40 x 10)/(50 x 50) + (48 x 10)/(50 x 80)
= 4/25 + 3/25 = 7/25
Now, 5 men and 8 women are removed after 10 days,
So work done by 35 men and 40 women in 10 days = (35 x 10)/(50 x 50) + (40 x 10)/(50 x 80)
= 7/50 + 1/10 = (7 + 5)/50
= 6/25
Again, 5 men and 8 women are removed after 10 days,
So work done by 30 men and 32 women in 10 days = (30 x 10)/(50 x 50) + (32 x 10)/(50 x 80) = 5/25
Now, after every 10 days as the number of men and
women decrease, work done also decreased by 1/25th past.
So, work done after every 10 days upto 50 days = 7/25 + 6/25 + 5/25 + 4/25 + 3/25
= 25/25 = 1
So, it will take 50 days for them to complete the work.
We have the important relation, More work, More time (days)
? A piece of work can be done in 6 days.
? Three times of work of same type can be done in 6 x 3
= 18 days
? = 750.0003 ÷ 19.999
? ? ? 750 ÷ 20
? ? ? 375 ? 38
Subtract 20, 25, 30, 35, 40, 45 from successive numbers. So 0 is wrong.
NA
Each previous number is multiplied by 2.
? 8 m shadow means original height = 12 m
? 1 m shadow means original height = 12/8 m
? 100 m shadow means original height = (12/8) x 100 m
= (6/4) x 100 = 6 x 25 = 150 m
Let 8% of 96 = y of 1/25
? (8 x 96)/100 = y/25
? y = (8 x 96 x 25)/100 = 192
Since the principal is not given, so data is inadequate.