  • Question
  • A can do a piece of work in 10 days. B can do it in 24 days. If C also works with them then it take only 6 days to complete the whole work. In how many days C alone can complete the whole work?


  • Options
  • A. 25
  • B. 40
  • C. 50
  • D. 75

  • Correct Answer
  • 40 

    Explanation

    Efficiency of A = 100/10 = 10%
    Efficiency of B = 100/24 = 4.16%
    Efficiency of (A+B+C) = 100/6 = 16.66%

    Efficiency of C = (16.66) - (10 + 4.16) = 2.5%
    Number of days required by C alone to finish the work = 100/2.5 = 40 days


  • Time and Work problems


    Search Results


    • 1. 
      A piece of work was to be completed in 40 days, a number of men employed upon it did only half the work in 24 days, 16 more men were then set on and the work was completed in the specified time, how many men were employed at first?

    • Options
    • A. 16 men
    • B. 32 men
    • C. 24 men
    • D. 48 men
    • Discuss
    • 2. 
      If 5 men and 3 boys can reap 23 hectares in 4 days and if 3 men and two boys can reap 7 hectares in 2 days. How many boys must assist 7 men in order that they may reap 45 hectares in 6 days?

    • Options
    • A. 2 boys
    • B. 6 boys
    • C. 4 boys
    • D. 5 boys
    • Discuss
    • 3. 
      14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more person joined them. How many days will they take to complete the remaining work?

    • Options
    • A. 12 days
    • B. 7 days
    • C. 9 days
    • D. None of these
    • Discuss
    • 4. 
      Typist A can type a report in 16 hours. Typist B can type the same report in 20 hours and the typist C in 24 hours. All the three typist started typing at 9.00 a.m. at 1.00 p.m. the typist A stopped typing. The other two typists finished the job. Approximately at what time the report was typed?

    • Options
    • A. 04 : 10 p.m.
    • B. 05 : 11 p.m.
    • C. 05 : 45 p.m.
    • D. 06 : 15 p.m.
    • Discuss
    • 5. 
      Twenty-four men can complete a work in sixteen days. Thirty-two women can complete the same work in twenty-four days. Sixteen men and Sixteen women started working and worked for twelve days. How many more men are to be added to complete the remaining work in 2 days?

    • Options
    • A. 48
    • B. 24
    • C. 36
    • D. None of these
    • Discuss
    • 6. 
      If 15 men can prepare 12 toys working 5 h per day in 16 days, then in how many days can 10 men prepare 15 toys working 8 h per day?

    • Options
    • A. 182/3 days
    • B. 183/4 days
    • C. 184/5 days
    • D. 185/7 days
    • Discuss
    • 7. 
      In a garrison, there was food for 1000 soldiers for one month. After 10 days, 1000 more soldiers joined the garrison. How long would the soldiers be able to carry on with the remaining food?

    • Options
    • A. 25 days
    • B. 20 days
    • C. 15 days
    • D. 10 days
    • Discuss
    • 8. 
      A and B can do a piece of work separately in 8 and 12 h. If they work alternate hours, A starting, when will the work be finished?

    • Options
    • A. 91/2 h
    • B. 9 h
    • C. 81/2 h
    • D. 8 h
    • Discuss
    • 9. 
      A contractor undertook to do a piece of work in 9 days. He employed a certain number of laborious but 6 of them being absent from the very first day, the rest could finish the work in 15 days. Find the number of men originally employed.

    • Options
    • A. 15
    • B. 6
    • C. 13
    • D. 9
    • Discuss
    • 10. 
      Two pipes A and B can each fill a tank in 40 and 60 min, respectively. There is an outlet C. If all the 3 pipes are opened up, the tank will be filled in 30 min. How much time will it take for C alone to empty the full tank?

    • Options
    • A. 1 h
    • B. 2 h
    • C. 3 h
    • D. 4 h
    • Discuss