logo

CuriousTab

CuriousTab

Discussion


Home Aptitude Time and Work Comments

  • Question
  • A can complete a job in 9 days, B in 10 days and C in 15 days. B and C start the work and are forced to leave after 2 days. The time taken to complete the remaining work is?


  • Options
  • A. 6 days
  • B. 9 days
  • C. 10 days
  • D. 13 days

  • Correct Answer
  • 6 days 

    Explanation

    (B + C)'s 2 day's work = 2 x (1/10 + 1/15) = 1/3
    Remaining work = (1 - 1/3) = 2/3
    ? 1/9 work is done by A in 1 day
    ? 2/3 work is done by A in (9 x 2) / 3 = 6 days


  • Time and Work problems


    Search Results


    • 1. 
      Twelve men can complete a work in 8 days. Three days after they started the work, 3 more men joined them. In how, many days will all of them together complete the remaining work

    • Options
    • A. 2
    • B. 4
    • C. 5
    • D. 6
    • Discuss
    • 2. 
      A can do a piece of work in 10 days and B can do the same piece of work in 20 days. They start the work together but after 5 days A leaves off, B will do the remaining piece of work in?

    • Options
    • A. 5 days
    • B. 6 days
    • C. 8 days
    • D. 10 days
    • Discuss
    • 3. 
      A completes a work in 15 days. B complete the same work in 20 days. A started working alone after 1 days B joined him. How many day will they now take together to complete the remaining work?

    • Options
    • A. 8 days
    • B. 7 days
    • C. 6 days
    • D. None of these
    • Discuss
    • 4. 
      A can do a piece of work in 12 days, B can do the same work in 8 days and c can do the same job in 4 / 5 th time required by both A and B. A and B work together for 3 days, then C complete days did C work?

    • Options
    • A. 8
    • B. 6
    • C. 3
    • D. None of these
    • Discuss
    • 5. 
      25 men and 15 women can complete a piece of work in 12 days. All of them start working together and after working for 8 days the women stopped working. 25 men complete the remaining work in 6 days. how many days will it take for completing the entire job if only 15 women are put on the job?

    • Options
    • A. 60 days
    • B. 88 days
    • C. 94 days
    • D. None of these
    • Discuss
    • 6. 
      Twenty-four men can complete a work in sixteen days. Thirty-two women can complete the same work in twenty-four days. Sixteen men and Sixteen women started working and worked for twelve days. How many more men are to be added to complete the remaining work in 2 days?

    • Options
    • A. 48
    • B. 24
    • C. 36
    • D. None of these
    • Discuss
    • 7. 
      Typist A can type a report in 16 hours. Typist B can type the same report in 20 hours and the typist C in 24 hours. All the three typist started typing at 9.00 a.m. at 1.00 p.m. the typist A stopped typing. The other two typists finished the job. Approximately at what time the report was typed?

    • Options
    • A. 04 : 10 p.m.
    • B. 05 : 11 p.m.
    • C. 05 : 45 p.m.
    • D. 06 : 15 p.m.
    • Discuss
    • 8. 
      14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more person joined them. How many days will they take to complete the remaining work?

    • Options
    • A. 12 days
    • B. 7 days
    • C. 9 days
    • D. None of these
    • Discuss
    • 9. 
      If 5 men and 3 boys can reap 23 hectares in 4 days and if 3 men and two boys can reap 7 hectares in 2 days. How many boys must assist 7 men in order that they may reap 45 hectares in 6 days?

    • Options
    • A. 2 boys
    • B. 6 boys
    • C. 4 boys
    • D. 5 boys
    • Discuss
    • 10. 
      A piece of work was to be completed in 40 days, a number of men employed upon it did only half the work in 24 days, 16 more men were then set on and the work was completed in the specified time, how many men were employed at first?

    • Options
    • A. 16 men
    • B. 32 men
    • C. 24 men
    • D. 48 men
    • Discuss


    Comments

    There are no comments.

Enter a new Comment