? In 5 days 14 workers make = 1400 toys.
? In 1 days 14 workers make toys = 1400/5 = 280 toys.
Number of remaining toys = 1400 - 280 = 1120
and number of total workers = 14 + 14 = 28
? 14 workers make 1400 toys in 5 days.
? 28 workers make 1120 toys = (5 x 14 x 1120)/(28 x 1400) = 2 days
We have the important relation, More work, More time (days)
? A piece of work can be done in 6 days.
? Three times of work of same type can be done in 6 x 3
= 18 days
? = 750.0003 ÷ 19.999
? ? ? 750 ÷ 20
? ? ? 375 ? 38
Subtract 20, 25, 30, 35, 40, 45 from successive numbers. So 0 is wrong.
NA
Each previous number is multiplied by 2.
? 8 m shadow means original height = 12 m
? 1 m shadow means original height = 12/8 m
? 100 m shadow means original height = (12/8) x 100 m
= (6/4) x 100 = 6 x 25 = 150 m
Let 8% of 96 = y of 1/25
? (8 x 96)/100 = y/25
? y = (8 x 96 x 25)/100 = 192
Since the principal is not given, so data is inadequate.