  • Question
  • 25 men reap a field in 20 days. When should 15 men leave the work, if the whole field is to be reaped in 37 1/ 2 day after they leave the work?


  • Options
  • A. 6 days
  • B. 4 days
  • C. 5 days
  • D. None of these

  • Correct Answer
  • 5 days 

    Explanation

    25 men reap the field in 20 days
    ? 10 men can reap the feild in (20 x 25)/ 10 = 50 days.
    When 15 men leave the work, 10 men remain and they can reap in 371/2 days
    = (371/2)/ 50 = 3/4 of the field
    Hence, all men must work till (1 - 3/4) = 1/4 of the field is reaped in 20/4 = 5 days.


  • Time and Work problems


    Search Results


    • 1. 
      A and B can do a piece of work in 72 days. B and C can do it in 120 days, A and C and do it in 90 days. In what time can A alone do it?

    • Options
    • A. 80 days
    • B. 100 days
    • C. 120 days
    • D. 150 days
    • Discuss
    • 2. 
      A and B can do a piece of work in 18 days. B and C in 24 days, C and A in 36 days. Find the time in which A, B and C working together can finish the work.

    • Options
    • A. 8
    • B. 16
    • C. 24
    • D. 36
    • Discuss
    • 3. 
      If 3 men or 4 women can built a wall in 43 days, in how many days can 7 men and 5 women build this wall?

    • Options
    • A. 16 days
    • B. 25 days
    • C. 21 days
    • D. 12 days
    • Discuss
    • 4. 
      45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to the employed will be?

    • Options
    • A. 50
    • B. 54
    • C. 60
    • D. 72
    • Discuss
    • 5. 
      20 men complete one-third of a work in 20 days. How many more men should be employed to finished the rest of work in 25 more days.?

    • Options
    • A. 15
    • B. 12
    • C. 18
    • D. 25
    • Discuss
    • 6. 
      A can do a piece of work in 5 hours, B in 9 hours and C in 15 hours. If C could work with them for 1 hour only the time taken by A and B together to complete the work is?

    • Options
    • A. 2 hours
    • B. 3 hours
    • C. 31/2
    • D. 4 hours
    • Discuss
    • 7. 
      A can do a piece of work in 24 days while B alone can do it in 16 days. But with the help of C, they finish the work in 8 days. C alone can do the work in?

    • Options
    • A. 32 days
    • B. 36 days
    • C. 40 days
    • D. 48 days
    • Discuss
    • 8. 
      A can do a certain job in 10 days. B is 60% more efficient than A. The number of days, it takes B to do the same piece of work is?

    • Options
    • A. 6
    • B. 61/4
    • C. 62/3
    • D. 8
    • Discuss
    • 9. 
      A, B and C together earn Rs. 150 per day while A and C together earn Rs. 94 and B and C together earn Rs. 76. The daily earning of C is?

    • Options
    • A. Rs. 75
    • B. Rs. 56
    • C. Rs. 34
    • D. Rs. 20
    • Discuss
    • 10. 
      A alone can finish a work in 10 days and B alone can do it in 15 days. If they work together and finish it, then out of a total wages of Rs. 75, A will get?

    • Options
    • A. Rs. 30
    • B. Rs. 37.50
    • C. Rs. 45
    • D. Rs. 50
    • Discuss


    Comments

    Avatar
    Aathiba
    Thanks


Enter a new Comment