  • Question
  • A is thrice efficient as B and C is twice as efficient as B. what is the ratio of number of days taken by A,B and C , when they work individually?


  • Options
  • A. 2 : 6 : 3
  • B. 2 : 3 : 6
  • C. 1 : 2 : 3
  • D. 3 : 1 : 2

  • Correct Answer
  • 2 : 6 : 3 

    Explanation

    A : B : C
    Ratio of efficiency 3 : 1 : 2
    Ratio of number of days { 1/3 : 1/1 : 1/2 }
    or 2 : 6 : 3
    Hence, (a) is correct [ Time = 1/ Efficiency ]


  • Time and Work problems


    Search Results


    • 1. 
      A can do a piece of work in 24 days, while B can do it in 30 days. With the help of C they can finish the whole work in 12 days.How much time is required for C to complete the work, alone?

    • Options
    • A. 100 days
    • B. 120 days
    • C. 125 days
    • D. 72 days
    • Discuss
    • 2. 
      A can do a piece of work in 10 days ,B can do it in 15 days. Working together they can finish the work in?

    • Options
    • A. 9
    • B. 8
    • C. 10
    • D. 6
    • Discuss
    • 3. 
      you can do a piece of work in 8 days, B can do it in 16,While C can do it in 80 days. In how many days they can complete the whole work, working together?

    • Options
    • A. 5
    • B. 6
    • C. 8 2/3
    • D. 20 2/5
    • Discuss
    • 4. 
      12 men can complete a work within 9 days. After 3 days they started the work, 6 men joined them to replace 2 men. How many days will they take to complete the remaining work?

    • Options
    • A. 2
    • B. 3
    • C. 4
    • D. 41/2
    • Discuss
    • 5. 
      14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work?

    • Options
    • A. 9 days
    • B. 5 days
    • C. 6 days
    • D. 7 days
    • Discuss
    • 6. 
      If A takes 4/5 days as B takes and working together they require 20/3 days to complete the whole work. What is the efficiency of B?

    • Options
    • A. 62/3%
    • B. 16%
    • C. 5.55%
    • D. 81/3%
    • Discuss
    • 7. 
      A is thrice as efficient as B. Working together they complete the work in 3 days. If B take 8 days more then A, What is the number of days taken by A to finish the while work, alone?

    • Options
    • A. 4
    • B. 2
    • C. 12
    • D. 16
    • Discuss
    • 8. 
      A and B can do a piece of work in 12 days B and C in 15 days C and A in 20 days. In how many days can C alone do it?

    • Options
    • A. 60
    • B. 50
    • C. 25
    • D. 24
    • Discuss
    • 9. 
      A and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work,working together?

    • Options
    • A. 4
    • B. 6
    • C. 12
    • D. 9
    • Discuss
    • 10. 
      A, B and C working in a garment manufacturing company can do the same assignment in 24, 6 and 12 days, respectively. Working together the assignment will be complete in how many days?

    • Options
    • A. 33/7 days
    • B. 43/7 days
    • C. 4 days
    • D. 3 days
    • Discuss