logo

CuriousTab

CuriousTab

Discussion


Home Aptitude Time and Work Comments

  • Question
  • Mahesh and Umesh can complete a work in 10 days and 15 days respectively. Umesh starts the work and after 5 days Mahesh also joins him. In all the work would be completed in?


  • Options
  • A. 7 days
  • B. 9 days
  • C. 11 days
  • D. None of these

  • Correct Answer
  • 9 days 

    Explanation

    Umesh's 5 day's work = 5 x (1/15) = 1/3
    Remaining work = (1 - 1/3) = 2/3
    (1/10 + 1/15) work is done by both in 1 day
    ? 2/3 work is done by both in 6 x (2/3) = 4 days
    Hence, the work was completed in 4 + 5 = 9 days.


  • Time and Work problems


    Search Results


    • 1. 
      Sunil complete a work in 4 days whereas Dinesh completes the work in 6 days. Ramesh work 1 1/ 2 times as fast as sunil. How many days it will take for the three together to complete the work?

    • Options
    • A. 7 / 12
    • B. 15/12
    • C. 15/7
    • D. None of these
    • Discuss
    • 2. 
      Ram, Dilip and Shekhar can complete a work in 20 days. If Ram and Dilip together can complete the same work in 30 days, then how long will Shekhar take to complete it?

    • Options
    • A. 60 days
    • B. 62 days
    • C. 40 days
    • D. 56 days
    • Discuss
    • 3. 
      A and B separately can complete a work in 6 days and 3 days respectively. If they work together, then in how many days will they complete the work?

    • Options
    • A. 4 days
    • B. 3 days
    • C. 2 days
    • D. 5 days
    • Discuss
    • 4. 
      A, B and C contract a work for Rs. 550. Together A and B are supposed to do 7/11 of the work. The share of C should be?

    • Options
    • A. Rs. 1831/3
    • B. Rs. 200
    • C. Rs. 300
    • D. Rs. 400
    • Discuss
    • 5. 
      10 men and 15 women finish a work in 6 days. One man alone finishes that work in 100 days. In how many days will one women can finish the work?

    • Options
    • A. 125 days
    • B. 150 days
    • C. 90 days
    • D. 225 days
    • Discuss
    • 6. 
      A can do a piece of work in 80 days. He works at it For 10 days and then B alone finishes the work in 42 days. The two together could complete the work in?

    • Options
    • A. 24 days
    • B. 25 days
    • C. 30 days
    • D. 35 days
    • Discuss
    • 7. 
      A can do a certain job in 25 days which B alone can do in 20 days. A started the work and was joined by B after 10 days. The work lasted for?

    • Options
    • A. 121/2
    • B. 142/9
    • C. 15 days
    • D. 162/3
    • Discuss
    • 8. 
      14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work?

    • Options
    • A. 9 days
    • B. 5 days
    • C. 6 days
    • D. 7 days
    • Discuss
    • 9. 
      12 men can complete a work within 9 days. After 3 days they started the work, 6 men joined them to replace 2 men. How many days will they take to complete the remaining work?

    • Options
    • A. 2
    • B. 3
    • C. 4
    • D. 41/2
    • Discuss
    • 10. 
      you can do a piece of work in 8 days, B can do it in 16,While C can do it in 80 days. In how many days they can complete the whole work, working together?

    • Options
    • A. 5
    • B. 6
    • C. 8 2/3
    • D. 20 2/5
    • Discuss


    Comments

    There are no comments.

Enter a new Comment