? One man alone finishes te work in 100 days.
? 10 men can finish the work in 10 day.
? 15 women can finish work in one days = 1/6 - 1/10 = 1/15 work
? 15 women finish the whole work in 15 days
? 1 women finishes the whole work in = 15 x 15 = 225 days
8M + 12W = 4 days (whole work)
? 32M + 48W = 1 day ................ (1)
Again 6M + 14W = 5 days
? 30M + 70W = 1 day ................(2)
From eq. (1) and (2)
32M + 48W = 30M +70W
? 2M = 22W
? 1M = 11W
Now, 30M + 70W = 1 day
(30 X 11 X 70)W = 1 day
Therefore 400W requires 1 day to complete the whole work.
Thus 20W needs 20 days to complete the whole work.
Ratio of time taken by X
and Y = 160 : 100 = 16 : 1
Suppose Y takes y days to the work.
Then, 1.6 : 1 = 16 : y
? y = (16 x 1)/1.6 = 10 days
Let time taken by B = N
Efficiency ? 1/Time taken
So, if B is 100% efficient, then A is 80% efficient.
So, 80/100 = N /(15/2)
? N = 6 h
A's 5 days' work = (1/15) x 5 = 1/3
Remaining work = 1 - (1/3) = 2/3
? (A + B)'s 1 day's work
= (1/15) + (1/10)
= (2 + 3(/30
= 5/30
= 1/6
? 2/3 work will be finished by (A + B) in (2/3) x 6 days or in 4 days .
? Total time taken = (5 + 4) days = 9 days
P,s 1 day's work = 1/12
Q's 1 day's work = 1/8
(P + Q)'s 1 day's work = (1/12) + (1/8)
= (2 + 3)/24
= 5/24
(P + Q + R)'s 1 day's work = 1/4
? R's 1 day's work = (1/4) - (5/24) = (6 - 5)/24 = 1/24
? R will finish the work alone in 24 days.
? Required time = 24 days
Work to be done by C = (1 - 7/11) = 4/11
? (A + B) : C = 7/11 : 4/11 = 7 : 4
? C's share = Rs. 550 x (4/11) = Rs. 200
Work completed by A + B in one day = 1/6 + 1/3 = 1/2
? Time taken by A + B to complete the work = 2 days.
? Work of (Ram + Dilip + Shekhar) for 1 day = 1/20
and work of (Ram + Dilip) for 1 day = 1/30
? Work of Shekhar for 1 day = 1 / 20 - 1 / 30 = 1/60
Hence, Shekhar will complete the work in 60 days.
Time taken by Ramesh alone = (2/3) x 4 = 8/3 days
? Their 1 day's work = (1/4 + 1/6 + 3/8) = 19/24
So, together they can finish the work in 24 /19 days, i.e., 15/19 days.
Umesh's 5 day's work = 5 x (1/15) = 1/3
Remaining work = (1 - 1/3) = 2/3
(1/10 + 1/15) work is done by both in 1 day
? 2/3 work is done by both in 6 x (2/3) = 4 days
Hence, the work was completed in 4 + 5 = 9 days.