  • Three taps A, B and C together can fill a tank in 6 h. After working 2 h, C is closed and the tank was filled in 8 h more. Find the time in which C alone can fill the tank?


  • Options
  • A. 12 h
  • B. 16 h
  • C. 14 h
  • D. 18 h

  • Correct Answer
  • 12 h 

    Explanation

    Work of (A + B + C) in 1 H = 1 / 6
    Work done in 2 h = 2/6 = 1/3
    Remaining part of the tank = 1 - 1/3 = 2/3
    Time taken by A + B to fill this 2/3rd part of the tank = 8 h
    A and B together can fill tank in 12 h (i.e., 8 x 3/2).
    Now, we have A, B and C together filling the tank in 6 h and A and B together fill tank in 12 h.
    Work done by C alone in 1 h = 1/6 - 1/12 = 1/12
    Hence, C alone can fill the tank in 12 h.


  • Time and Work problems


    Search Results


    • 1. 
      Sonu can do a piece of work in 20 days. He started the work and left after some days, when 25% work was done. After it Abhijeet joined and completed it working for 10 days. In how many days Sonu and Abhijeet can do the complete work, working together?

    • Options
    • A. 6
    • B. 8
    • C. 10
    • D. 12
    • Discuss
    • 2. 
      X is 4 times more efficient as Y , then the number of days taken by X and Y are in the ratio?

    • Options
    • A. 8 : 1
    • B. 1 : 5
    • C. 6 : 8
    • D. 5 : 1
    • Discuss
    • 3. 
      Ajit is 3 times as efficient as Bablu, then the ratio of number of days required by each to work alone, completely?

    • Options
    • A. 3 : 1
    • B. 1 : 3
    • C. 6 : 3
    • D. 3 : 6
    • Discuss
    • 4. 
      A is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can a alone finish the work?

    • Options
    • A. 18
    • B. 20
    • C. 21
    • D. 24
    • Discuss
    • 5. 
      A can do a piece of work in 24 days. If B is 60% more efficient than A, then the number of days required by B to do the same piece of work is?

    • Options
    • A. 10
    • B. 15
    • C. 12
    • D. 9.6
    • Discuss
    • 6. 
      Alen and Border can do a work individually in 21 and 42 days respectively. In how many days they can complete the work, working alternatively?


    • Options
    • A. 14
    • B. 28
    • C. 42
    • D. 35
    • Discuss
    • 7. 
      If 12 man or 18 women can do piece of work in 14 days. How long will 8 men and 16 women take to finish the work?

    • Options
    • A. 9 days
    • B. 12 days
    • C. 13 days
    • D. 10 days
    • Discuss
    • 8. 
      10 man can make a wall in 8 days. How many men required to complete the same work in half days?

    • Options
    • A. 80
    • B. 100
    • C. 120
    • D. 160
    • Discuss
    • 9. 
      6 boys can complete a piece of work in 16 h. In how many hours will 8 boys complete the same work?

    • Options
    • A. 10
    • B. 8
    • C. 12
    • D. 14
    • Discuss
    • 10. 
      In a hostel, there are 120 students and food stock is for 45 days. If 30 new students join the hostel, in how many days will the complete stock be exhausted?

    • Options
    • A. 38
    • B. 40
    • C. 32
    • D. 36
    • Discuss