logo

CuriousTab

CuriousTab

Discussion


Home Aptitude Time and Work Comments

  • Question
  • A and B together can do a work in 8 days. If A alone can do it in 12 days, then in how many days can B alone do it?


  • Options
  • A. 12 days
  • B. 20 days
  • C. 24 days
  • D. 28 days

  • Correct Answer
  • 24 days 

    Explanation

    Required time taken by B to complete the work = xy / x - y
    [Here x = 12 and y = 8]
    ? required time = (12 x 8) / (12 - 8) = 96/4 = 24 days


  • Time and Work problems


    Search Results


    • 1. 
      A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in?

    • Options
    • A. 3 days
    • B. 5 days
    • C. 7 days
    • D. 11 days
    • Discuss
    • 2. 
      A can do (1/3) of a work in 5 days and B can do (2/5) of the work in 10 days. In how many days both A and B together can do the work?

    • Options
    • A. 73/4
    • B. 84/5
    • C. 93/8
    • D. 10
    • Discuss
    • 3. 
      A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?

    • Options
    • A. 70 days
    • B. 423/4 days
    • C. 271/7 days
    • D. 171/7 days
    • Discuss
    • 4. 
      A and B can do a piece of work in 12 days. B and C in 15 days. C and A in 20 days. A alone can do the work in?

    • Options
    • A. 152/3
    • B. 24 days
    • C. 30 days
    • D. 4 days
    • Discuss
    • 5. 
      A and B can do a piece of work in 18 days, B and C in 24 days, A and C in 36 days. In what time can they do it all working together?

    • Options
    • A. 12 days
    • B. 13 days
    • C. 16 days
    • D. 26 days
    • Discuss
    • 6. 
      Rohan and Sunil separately can complete a work in 8 hours and 4 hours respectively. How much time will they take when working together?

    • Options
    • A. 22/3
    • B. 11/3
    • C. 3 hours
    • D. 2 hours
    • Discuss
    • 7. 
      A can do a piece of work in 12 days. B is 60% more efficient than A. The number of days, it take B to do the same piece of work is?

    • Options
    • A. 71/2
    • B. 61/4
    • C. 8
    • D. 6
    • Discuss
    • 8. 
      A can finish a piece of work in 12 days while B can do it in 15 days. If both work at it together, what time will they take to do the work?

    • Options
    • A. 6 days
    • B. 8 days
    • C. 62/3 days
    • D. 101/15 days
    • Discuss
    • 9. 
      A can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?

    • Options
    • A. 10.5
    • B. 8
    • C. 8.4
    • D. 9
    • Discuss
    • 10. 
      A can do a piece of work in 24 days. If B is 60% more efficient than A, then the number of days required by B to do the same piece of work is?

    • Options
    • A. 10
    • B. 15
    • C. 12
    • D. 9.6
    • Discuss


    Comments

    There are no comments.

Enter a new Comment