  • Question
  • A can do (1/3) of a work in 5 days and B can do (2/5) of the work in 10 days. In how many days both A and B together can do the work?


  • Options
  • A. 73/4
  • B. 84/5
  • C. 93/8
  • D. 10

  • Correct Answer
  • 93/8 

    Explanation

    ? 1/3 of work is done by A in 5 days.
    ? Whole work will be done by A in 15 days.
    ? 2/3 of work is done by B in 10 days.
    Whole work will be done by B in 10 x (5/2) i.e., 25days

    ? (A + B)'s 1 day's work = (1/15 + 1/25) = 8/75
    So, both together can finish it in 75/8 days, i.e., 93/8days.


  • Time and Work problems


    Search Results


    • 1. 
      A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?

    • Options
    • A. 70 days
    • B. 423/4 days
    • C. 271/7 days
    • D. 171/7 days
    • Discuss
    • 2. 
      A and B can do a piece of work in 12 days. B and C in 15 days. C and A in 20 days. A alone can do the work in?

    • Options
    • A. 152/3
    • B. 24 days
    • C. 30 days
    • D. 4 days
    • Discuss
    • 3. 
      A and B can do a piece of work in 18 days, B and C in 24 days, A and C in 36 days. In what time can they do it all working together?

    • Options
    • A. 12 days
    • B. 13 days
    • C. 16 days
    • D. 26 days
    • Discuss
    • 4. 
      A and B can do a piece of work in 6 days and A alone can do it in 9 days. The time taken by B alone to do the same work is?

    • Options
    • A. 18 days
    • B. 15 days
    • C. 12 days
    • D. 71/2
    • Discuss
    • 5. 
      A and B can together do a piece of work in 15 days. B alone can do it 20 days. In how many days can A alone do it?

    • Options
    • A. 30 days
    • B. 40 days
    • C. 45 days
    • D. 60 days
    • Discuss
    • 6. 
      A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in?

    • Options
    • A. 3 days
    • B. 5 days
    • C. 7 days
    • D. 11 days
    • Discuss
    • 7. 
      A and B together can do a work in 8 days. If A alone can do it in 12 days, then in how many days can B alone do it?

    • Options
    • A. 12 days
    • B. 20 days
    • C. 24 days
    • D. 28 days
    • Discuss
    • 8. 
      Rohan and Sunil separately can complete a work in 8 hours and 4 hours respectively. How much time will they take when working together?

    • Options
    • A. 22/3
    • B. 11/3
    • C. 3 hours
    • D. 2 hours
    • Discuss
    • 9. 
      A can do a piece of work in 12 days. B is 60% more efficient than A. The number of days, it take B to do the same piece of work is?

    • Options
    • A. 71/2
    • B. 61/4
    • C. 8
    • D. 6
    • Discuss
    • 10. 
      A can finish a piece of work in 12 days while B can do it in 15 days. If both work at it together, what time will they take to do the work?

    • Options
    • A. 6 days
    • B. 8 days
    • C. 62/3 days
    • D. 101/15 days
    • Discuss