logo

CuriousTab

CuriousTab

Discussion


Home Aptitude Time and Work Comments

  • Question
  • A and B can do a piece of work in 18 days, B and C in 24 days, A and C in 36 days. In what time can they do it all working together?


  • Options
  • A. 12 days
  • B. 13 days
  • C. 16 days
  • D. 26 days

  • Correct Answer
  • 16 days 

    Explanation

    (A + B)'s 1 day's work = 1/18
    (B + C)'s 1 day's work = 1/24
    (A + C)'s 1 day's work = 1/36
    Adding 2 (A + B + C)'s 1 day's work = (1/18 + 1/24 + 1/36) = 1/8
    ? (A + B + C)'s day's work = 1/16
    Hence, all working together can finish it in 16 days.

  • Tags: Bank Exams

    Time and Work problems


    Search Results


    • 1. 
      A and B can do a piece of work in 6 days and A alone can do it in 9 days. The time taken by B alone to do the same work is?

    • Options
    • A. 18 days
    • B. 15 days
    • C. 12 days
    • D. 71/2
    • Discuss
    • 2. 
      A and B can together do a piece of work in 15 days. B alone can do it 20 days. In how many days can A alone do it?

    • Options
    • A. 30 days
    • B. 40 days
    • C. 45 days
    • D. 60 days
    • Discuss
    • 3. 
      20 persons completed 1/3rd of the work in 12 days. How many more person are required to finish the rest work in next 12 days?

    • Options
    • A. 20
    • B. 12
    • C. 18
    • D. 40
    • Discuss
    • 4. 
      A contractor undertook a work to complete in 60 days. But just after 20 days he observed that only 1/5th of the project work had been completed. To complete the work in time (i.e,In rest days) minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?

    • Options
    • A. 25
    • B. 50
    • C. 75
    • D. can't be determined
    • Discuss
    • 5. 
      If 2 men or 3 women or 4 boys can do a piece of work in 52 days. Then the same piece of work will be done by 1 man, 1 woman and 1 boy in?

    • Options
    • A. 48 days
    • B. 36 days
    • C. 45 days
    • D. none of these
    • Discuss
    • 6. 
      A and B can do a piece of work in 12 days. B and C in 15 days. C and A in 20 days. A alone can do the work in?

    • Options
    • A. 152/3
    • B. 24 days
    • C. 30 days
    • D. 4 days
    • Discuss
    • 7. 
      A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?

    • Options
    • A. 70 days
    • B. 423/4 days
    • C. 271/7 days
    • D. 171/7 days
    • Discuss
    • 8. 
      A can do (1/3) of a work in 5 days and B can do (2/5) of the work in 10 days. In how many days both A and B together can do the work?

    • Options
    • A. 73/4
    • B. 84/5
    • C. 93/8
    • D. 10
    • Discuss
    • 9. 
      A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in?

    • Options
    • A. 3 days
    • B. 5 days
    • C. 7 days
    • D. 11 days
    • Discuss
    • 10. 
      A and B together can do a work in 8 days. If A alone can do it in 12 days, then in how many days can B alone do it?

    • Options
    • A. 12 days
    • B. 20 days
    • C. 24 days
    • D. 28 days
    • Discuss


    Comments

    There are no comments.

Enter a new Comment