  • Question
  • The Ratio of efficiencies of A, B and C is 6 : 5 : 4 and if A, B and C received total Rs. 27000 for the whole work. What is the share of C, if the money is distributed in the ratio of amount of work done, individually?


  • Options
  • A. 2700
  • B. 7200
  • C. 14400
  • D. 6300

  • Correct Answer
  • 7200 

    Explanation

    Ratio of efficiencies of A,B and C = 6 : 5 : 4
    ? Share of C = [4/(6+5+4)] x 27000 = 7200


  • Time and Work problems


    Search Results


    • 1. 
      314 weavers weaves 6594 shawls in 1/6 hours. What is the number of shawls weaved per hour by an average weaver?

    • Options
    • A. 42
    • B. 21
    • C. 102
    • D. 126
    • Discuss
    • 2. 
      2 men or 5 women or 7 boys can finish a work in 469 days, then the number of days taken by 7 men, 5 women and 2 boys to finish the work is :

    • Options
    • A. 134
    • B. 106
    • C. 100
    • D. 98
    • Discuss
    • 3. 
      6 children and 2 men complete a certain piece of work in 6 days. Each child takes twice the time taken by a man to finish the work. In how many days will 5 men finish the same work?

    • Options
    • A. 6
    • B. 8
    • C. 9
    • D. 15
    • Discuss
    • 4. 
      6 men or 10 women can reap a field in 15 days, then the number of days that 12 men and 5 women will take to reap the same field is :

    • Options
    • A. 5
    • B. 6
    • C. 8
    • D. 12
    • Discuss
    • 5. 
      A man travels 35 km partly at 4 km/hr and at 5 km/hr. If he covers former distance at 5 km/hr and later distance at 4 km/hr, he could cover 2 km more in the same time. The time taken to cover the whole distance at original rate is

    • Options
    • A. 9 hours
    • B. 7 hours
    • C. 4.5 hours
    • D. 8 hours
    • Discuss
    • 6. 
      If 2 men or 3 women or 4 boys can do a piece of work in 52 days. Then the same piece of work will be done by 1 man, 1 woman and 1 boy in?

    • Options
    • A. 48 days
    • B. 36 days
    • C. 45 days
    • D. none of these
    • Discuss
    • 7. 
      A contractor undertook a work to complete in 60 days. But just after 20 days he observed that only 1/5th of the project work had been completed. To complete the work in time (i.e,In rest days) minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?

    • Options
    • A. 25
    • B. 50
    • C. 75
    • D. can't be determined
    • Discuss
    • 8. 
      20 persons completed 1/3rd of the work in 12 days. How many more person are required to finish the rest work in next 12 days?

    • Options
    • A. 20
    • B. 12
    • C. 18
    • D. 40
    • Discuss
    • 9. 
      A and B can together do a piece of work in 15 days. B alone can do it 20 days. In how many days can A alone do it?

    • Options
    • A. 30 days
    • B. 40 days
    • C. 45 days
    • D. 60 days
    • Discuss
    • 10. 
      A and B can do a piece of work in 6 days and A alone can do it in 9 days. The time taken by B alone to do the same work is?

    • Options
    • A. 18 days
    • B. 15 days
    • C. 12 days
    • D. 71/2
    • Discuss