A, B and C contract to do a work for ? 4200. A can do the work in 6 days, B in 10 days and C in 12 days.
From given question, As we know that
A can do the work in 6 days.
A can do 1/6 work in one day.
B can do the same work in 10 days.
B can do 1/10 work in one day.
C can do the same work in 12 days.
C can do 1/12 work in one day.
Work done shared by A : B : C = 1/6 : 1/10 : 1/12
Multiply by 60, we will get,
Work done shared by A : B : C = 10 : 6 : 5
Let us assume ration variable is P.
According to question,
10P + 6P + 5P = 4200
? 21P = 4200
? P = 200
A's share = 10P = 10 x 200 = ? 2000
B's share = 6P = 6 x 200 = ? 1200,
C's share = 5P = 5 x 200 = ? 1000
A can do a work in 12 days.
? Work done by A = 1/12
B can do a work in 16 days.
? Work done by A = 1/16
Ration of Work done by A : Ration of Work done by B = 1/12 : 1/16
Ration of Work done by A : Ration of Work done by B = 4 : 3
A's shares = 2100 x 4/7 = 300 x 4 = ? 1200
B's share = 2100 x 3/7 = 300 x 3 = ? 900
It is required to find the highest common factor of 5750 and 5000, because his daily wage is their common factor.
Hence, the daily wage is ? 250.
The ratio of efficiency of man to boy
= 6 : 1
Efficiency ? Wages
? Boy's share = [1 / (1+6)] x 1400
(1/7) x 1400 = ? 200
Now, they worked for 10 days.
? Daily wages of a boy = 200/10 = ? 20
A's 1 day's work = 1/3
B's 1 day's work = 1/4
A's share : B's share
= (1/3) : (1/4) = (4/12) : (3/12)
= 4 : 3
A's share = (4/7) x 2800
= 4 x 400
= ? 1600