  • Question
  • A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the begining and 100 more after 35 days and completes the work in stipulated time.
    If he had not engaged the additional men, how many days behind schedule would it be finished?


  • Options
  • A. 7
  • B. 18
  • C. 12
  • D. None

  • Correct Answer
  • None 

    Explanation


  • Unitary Method problems


    Search Results


    • 1. 
      A wheel that has 6 cogs is meshed with a larger wheel of 14 cogs. When the smaller wheel has made 21 revolutions, then the number of revolutions made by the larger wheel is:

    • Options
    • A. 4
    • B. 9
    • C. 14
    • D. 7
    • Discuss
    • 2. 
      If 20 men can build a wall 56 meters long in 6 days , what length of a similar wall can be built by 35 men in 3 days?

    • Options
    • A. 40
    • B. 43
    • C. 48
    • D. 49
    • Discuss
    • 3. 
      2 men and 7 boys can do a piece of work in 14 days; 3 men and 8 boys can do the same in 11 days. Then, 8 men and 6 boys can do three times the amount of this work in.

    • Options
    • A. 18
    • B. 21
    • C. 34
    • D. 39
    • Discuss
    • 4. 
      If 40 men can make 30 boxes in 20 days, How many more men are needed to make 60 boxes in 25 days?

    • Options
    • A. 20
    • B. 24
    • C. 27
    • D. 28
    • Discuss
    • 5. 
      Nine engines consume 24 metric tonnes of coal, when each is working 8 hours day. How much coal is required for 8 engines, each running 13 hours a day, if 3 engines of former type consume as much as 4 engines of latter type?

    • Options
    • A. 20 metric tonnes
    • B. 39 metric tonnes
    • C. 23 metric tonnes
    • D. 26 metric tonnes
    • Discuss
    • 6. 
      36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work?

    • Options
    • A. 24
    • B. 23
    • C. 34
    • D. 39
    • Discuss
    • 7. 
      Some persons can do a piece of work in 12 days. Two times the number of such persons will do half of that work in :

    • Options
    • A. 16
    • B. 12
    • C. 8
    • D. 3
    • Discuss
    • 8. 
      If 36 men can do a piece of work in 25 hours, in how many hours will 15 men do it?

    • Options
    • A. 45
    • B. 55
    • C. 60
    • D. 72
    • Discuss
    • 9. 
      The Fourth term of an Arithmetic Progression is 37 and the Sixth term is 12 more than the Fourth term. What is the sum of the Second and Eight terms?

    • Options
    • A. 54
    • B. 64
    • C. 74
    • D. 84
    • Discuss
    • 10. 
      How many 3-digits numbers are completely divisible by 6?

    • Options
    • A. 149
    • B. 150
    • C. 151
    • D. 166
    • Discuss


    Comments

    There are no comments.

Enter a new Comment