In seive plate column, holes are drilled or punched in sizes ranging from 2.5 to 12 mm (5 mm being widely used). The hole pitch is normally __________ times the hole diameter to give the required hole area.
Options
A. 0.5 to 1.5
B. 2.5 to 4.0
C. 5 to 10
D. 10 to 15
Correct Answer
2.5 to 4.0
Process Equipment and Plant Design problems
Search Results
1. Pick out the wrong statement pertaining to the design of a long tube vertical evaporator.
Options
A. Tube dia is 3-6 cms, while tube length in 3-6 metres.
B. Steam is fed to the shell, whereas the liquor is filled inside the tube.
C. Liquor level is maintained at l/3rd to 1/2 of the height of the tube.
4. In packed towers provided with pall rings liquid redistributors are positioned at heights of every 6 metres or 5-10 times the column diameter, whichever is less. Maximum size of the pall rings should not exceed __________ of the column diameter.