  • Question
  • PERT


  • Options
  • A. provides an approach for keeping planning up-to-date
  • B. provides a way for management to require that planning be done on a uniform and logical basis
  • C. permits management to foresee quickly the impact of variations from the plan
  • D. all of the above

  • Correct Answer
  • all of the above 


  • Industrial Engineering and Production Management problems


    Search Results


    • 1. The value engineering technique in which experts of the same rank assemble for product development is called

    • Options
    • A. Delphi
    • B. brain storming
    • C. morphological analysis
    • D. direct expert comparison
    • Discuss
    • 2. Linear programming can be applied successfully to

    • Options
    • A. chemical industry
    • B. oil industry
    • C. banks
    • D. all of these
    • Discuss
    • 3. If A is the total items consumed per year, P is the procurement cost per order, and C is the annual inventory carrying cost per item, then the most economic ordering quantity is given by

    • Options
    • A.
    • B.
    • C.
    • D.
    • Discuss
    • 4. Travel charts are used to

    • Options
    • A. analyse material handling
    • B. determine inventory control difficulties
    • C. plan material handling procedure and routes
    • D. all of the above
    • Discuss
    • 5. Halsey plan of wage incentive

    • Options
    • A. is not applied to all level of workers
    • B. is applied to all level of workers
    • C. does not guarantee minimum wage
    • D. is based upon efficiency of worker
    • Discuss
    • 6. Which one of the following techniques is used for determining allowances in time study?

    • Options
    • A. Acceptance sampling
    • B. Linear regression
    • C. Performance rating
    • D. Work sampling
    • Discuss
    • 7. CPM requires

    • Options
    • A. single time estimate
    • B. double time estimate
    • C. triple time estimate
    • D. none of these
    • Discuss
    • 8. For handling materials during manufacture of cement, a __________ is widely used.

    • Options
    • A. belt conveyor
    • B. bucket conveyor
    • C. fork lift truck
    • D. overhead crane
    • Discuss
    • 9. The most suitableincentive plan for the maintenance section of an industry will be

    • Options
    • A. piece rate system
    • B. group incentive plan
    • C. profit sharing plans
    • D. simplification
    • Discuss
    • 10. The interchangeability can be achieved by

    • Options
    • A. standardisation
    • B. better process planning
    • C. bonus plan
    • D. better product planning
    • Discuss


    Comments

    There are no comments.

Enter a new Comment