  • A. plan and schedule of production
  • B. formulate a proper incentive scheme
  • C. estimate the selling prices and delivery dates
  • D. all of the above

  • Correct Answer
  • all of the above 


  • Industrial Engineering and Production Management problems


    Search Results


    • 1. When slack of an activity is zero, the activity is critical and any delay in its performance will delay the completion of the whole project.

    • Options
    • A. Yes
    • B. No
    • Discuss
    • 2. PERT stands for

    • Options
    • A. Programme Estimation and Reporting Technique
    • B. Process Estimation and Review Technique
    • C. Programme Evaluation and Review Technique
    • D. Planning Estimation and Resulting Technique
    • Discuss
    • 3. Merit rating is the method of determining the

    • Options
    • A. relative values of a job
    • B. worker's performance on a job
    • C. worth of a machine
    • D. value of overall production
    • Discuss
    • 4. The product layout

    • Options
    • A. lowers overall manufacturing time
    • B. requires less space for placing machines
    • C. utilises machine and labour better
    • D. all of these
    • Discuss
    • 5. In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker

    • Options
    • A. whose output exceeds 67% efficiency
    • B. on the percentage of time saved
    • C. on the percentage of time worked
    • D. on the percentage of standard time
    • Discuss
    • 6. Critical path method

    • Options
    • A. helps in ascertaining time schedules
    • B. makes better and detailed planning possible
    • C. provides a standard method for communicating project plans schedules and to time and cost performance
    • D. all of the above
    • Discuss
    • 7. The bonus increases in proportion to the increase in efficiency. This statement applies to

    • Options
    • A. Halsey plan
    • B. Ganttplan
    • C. Emerson's efficiency plan
    • D. Rowan plan
    • Discuss
    • 8. A-B-C analysis

    • Options
    • A. is a basic technique of materials management
    • B. is meant for relative inventory control
    • C. does not depend upon the unit cost of the item but on its annual consumption
    • D. all of the above
    • Discuss
    • 9. Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is __________ the standard time.

    • Options
    • A. one-fourth
    • B. one-half
    • C. equal to
    • D. twice
    • Discuss
    • 10. The work study is done by means of

    • Options
    • A. planning chart
    • B. process chart
    • C. stop watch
    • D. any one of these
    • Discuss