  • Which of the following statement is correct?


  • Options
  • A. When slack of an activity is zero, it falls only on critical path.
  • B. CPM technique is useful to minimise the direct and indirect expenses.
  • C. Critical path of a net work represents the minimum time required for completion of project.
  • D. all of the above

  • Correct Answer
  • all of the above 


  • Industrial Engineering and Production Management problems


    Search Results


    • 1. For material transportation, conveyors are used when the prevailing conditions include

    • Options
    • A. loads are uniform
    • B. routes do not vary
    • C. materials move relatively continuously
    • D. all of these
    • Discuss
    • 2. Follow-up prescribes the sequence of operations to be followed.

    • Options
    • A. Correct
    • B. Incorrect
    • Discuss
    • 3. A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

    • Options
    • A. 0.50
    • B. 0.66
    • C. 0.84
    • D. 0.95
    • Discuss
    • 4. Product layout is best suited where

    • Options
    • A. one type of product is produced
    • B. product is standardised
    • C. product is manufactured in large quantities
    • D. all of the above
    • Discuss
    • 5. An event is a function of two or more activities.

    • Options
    • A. Correct
    • B. Incorrect
    • Discuss
    • 6. The purpose of micromotion study is to

    • Options
    • A. assist in finding out the most efficient way of doing work
    • B. train the individual operator regarding the motion economy principles
    • C. help in collecting the motion time data for synthetic time standards
    • D. all of the above
    • Discuss
    • 7. Slack represents the difference between the

    • Options
    • A. earliest completion time and latest allowable time
    • B. latest allowable time and earliest completion time
    • C. earliest completion time and normal expected time
    • D. latest allowable time and normal allowable time
    • Discuss
    • 8. The factors to be considered for production scheduling are

    • Options
    • A. component design
    • B. route sheet
    • C. time standards
    • D. all of these
    • Discuss
    • 9. In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker

    • Options
    • A. whose output exceeds 67% efficiency
    • B. on the percentage of time saved
    • C. on the percentage of time worked
    • D. on the percentage of standard time
    • Discuss
    • 10. The product layout

    • Options
    • A. lowers overall manufacturing time
    • B. requires less space for placing machines
    • C. utilises machine and labour better
    • D. all of these
    • Discuss


    Comments

    There are no comments.

Enter a new Comment