  • Question
  • If F is the fixed cost, V is the variable cost per unit (or total variable costs) and P is the selling price of each unit (or total sales value), then break even point is equal to


  • Options
  • A. If F is the fixed cost, V is the variable cost per unit (or total variable costs) and P is the selli
  • B. If F is the fixed cost, V is the variable cost per unit (or total variable costs) and P is the selli
  • C. If F is the fixed cost, V is the variable cost per unit (or total variable costs) and P is the selli
  • D. If F is the fixed cost, V is the variable cost per unit (or total variable costs) and P is the selli

  • Correct Answer
  •  


  • Industrial Engineering and Production Management problems


    Search Results


    • 1. The increase in depth of cut and feed rate __________ surface finish.

    • Options
    • A. improves
    • B. deteriorates
    • C. does not effect
    • Discuss
    • 2. The infeed grinding is used to

    • Options
    • A. produce tapers
    • B. grind shoulders and formed surfaces
    • C. grind long, slender shafts or bars
    • D. ail of these
    • Discuss
    • 3. A diamond locating pin is used in jigs and fixtures because

    • Options
    • A. diamond is very hard and wear resistant
    • B. it occupies very little space
    • C. it helps in assembly with tolerance on centre distance
    • D. it has a long life
    • Discuss
    • 4. The operation performed on a shaper is

    • Options
    • A. machining horizontal surface
    • B. machining vertical surface
    • C. machining angular surface
    • D. all of these
    • Discuss
    • 5. In metal machining, the zone where the heat is generated due to friction between the moving chip and the tool face, is called

    • Options
    • A. friction zone
    • B. work-tool contact zone
    • C. shear zone
    • D. none of these
    • Discuss
    • 6. A critical activity has

    • Options
    • A. maximum slack
    • B. minimum slack
    • C. zero slack
    • D. average slack
    • Discuss
    • 7. A dummy activity in a net work diagram

    • Options
    • A. is represented by a dotted line
    • B. is an artificial activity
    • C. does not consume time or resources
    • D. all of these
    • Discuss
    • 8. In a thermal power plant, coal from the coal handling plant is moved to the boiler bunker through a

    • Options
    • A. belt conveyor
    • B. bucket conveyor
    • C. fork lift truck
    • D. overhead crane
    • Discuss
    • 9. In value engineering, important consideration is given to

    • Options
    • A. customer satisfaction
    • B. function concept
    • C. profit maximisation
    • D. cost reduction
    • Discuss
    • 10. When slack of an activity is positive

    • Options
    • A. it represents a situation where extra resources are available and the completion of project is not delayed
    • B. it represents that a programme falls behind schedule and additional resources are required to complete the project in time
    • C. the activity is critical and any delay in its performance will delay the completion of whole project
    • D. any one of the above
    • Discuss