logo

CuriousTab

CuriousTab

Discussion


Home Mechanical Engineering Industrial Engineering and Production Management Comments

  • Question
  • PERT requires


  • Options
  • A. single time estimate
  • B. double time estimate
  • C. triple time estimate
  • D. none of these

  • Correct Answer
  • triple time estimate 


  • Industrial Engineering and Production Management problems


    Search Results


    • 1. The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time)

    • Options
    • A.
    • B.
    • C.
    • D.
    • Discuss
    • 2. A-B-C analysis is used in

    • Options
    • A. CPM
    • B. PERT
    • C. inventory control
    • D. all of these
    • Discuss
    • 3. In break even analysis, total cost consists of

    • Options
    • A. fixed cost + sales revenue
    • B. variable cost + sales revenue
    • C. fixed cost + variable cost
    • D. fixed cost + variable cost + profit
    • Discuss
    • 4. Gantt chart is used for

    • Options
    • A. inventory control
    • B. material handling
    • C. production schedule
    • D. machine repair schedules
    • Discuss
    • 5. Which of the following are the guidelines for the construction of a network diagram?

    • Options
    • A. Each activity is represented by one and only one arrow in the network.
    • B. Dangling must be avoided in a network diagram.
    • C. Dummy activity consumes no time or resource.
    • D. all of the above
    • Discuss
    • 6. Linear programming model can be applied to line balancing problem and transportation problem.

    • Options
    • A. True
    • B. False
    • Discuss
    • 7. When slack of an activity is negative

    • Options
    • A. it represents a situation where extra resources are available and the completion of project is not delayed
    • B. it represents that a programme falls behind schedule and additional resources are required to complete the project in time
    • C. the activity is critical and any delay in its performance will delay the completion of whole project
    • D. all of the above
    • Discuss
    • 8. The limit of eccentricity is based upon no tension condition.

    • Options
    • A. True
    • B. False
    • Discuss
    • 9. A load which is spread over a beam in such a manner that it varies uniformly over the whole length of abeam is called uniformly __________ load.

    • Options
    • A. distributed
    • B. varying
    • Discuss
    • 10. The rectangular beam 'A' has length l, width b and depth d. Another beam 'B' has the same length and depth but width is double that of 'A'. The elastic strength of beam 'B' will be __________ as compared to beam A.

    • Options
    • A. same
    • B. double
    • C. four times
    • D. six times
    • Discuss


    Comments

    There are no comments.

Enter a new Comment