  • Question
  • In break even analysis, total cost consists of


  • Options
  • A. fixed cost + sales revenue
  • B. variable cost + sales revenue
  • C. fixed cost + variable cost
  • D. fixed cost + variable cost + profit

  • Correct Answer
  • fixed cost + variable cost 


  • Industrial Engineering and Production Management problems


    Search Results


    • 1. Gantt chart is used for

    • Options
    • A. inventory control
    • B. material handling
    • C. production schedule
    • D. machine repair schedules
    • Discuss
    • 2. Which of the following are the guidelines for the construction of a network diagram?

    • Options
    • A. Each activity is represented by one and only one arrow in the network.
    • B. Dangling must be avoided in a network diagram.
    • C. Dummy activity consumes no time or resource.
    • D. all of the above
    • Discuss
    • 3. String diagram is used

    • Options
    • A. for checking the relative values of various layouts
    • B. when a group of workers are working at a place
    • C. where processes require the operator to be moved from one work place to another
    • D. all of the above
    • Discuss
    • 4. Dispatching

    • Options
    • A. prescribes the sequence of operations to be followed
    • B. determines the programme for the operations
    • C. is concerned with the starting of processes
    • D. regulates the progress of job through various processes
    • Discuss
    • 5. Work study involues

    • Options
    • A. only method study
    • B. only work measurement
    • C. method study and work measurement
    • D. only motion study
    • Discuss
    • 6. A-B-C analysis is used in

    • Options
    • A. CPM
    • B. PERT
    • C. inventory control
    • D. all of these
    • Discuss
    • 7. The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time)

    • Options
    • A.
    • B.
    • C.
    • D.
    • Discuss
    • 8. PERT requires

    • Options
    • A. single time estimate
    • B. double time estimate
    • C. triple time estimate
    • D. none of these
    • Discuss
    • 9. Linear programming model can be applied to line balancing problem and transportation problem.

    • Options
    • A. True
    • B. False
    • Discuss
    • 10. When slack of an activity is negative

    • Options
    • A. it represents a situation where extra resources are available and the completion of project is not delayed
    • B. it represents that a programme falls behind schedule and additional resources are required to complete the project in time
    • C. the activity is critical and any delay in its performance will delay the completion of whole project
    • D. all of the above
    • Discuss