logo

CuriousTab

CuriousTab

Discussion


Home Mechanical Engineering Industrial Engineering and Production Management Comments

  • Question
  • Dispatching


  • Options
  • A. prescribes the sequence of operations to be followed
  • B. determines the programme for the operations
  • C. is concerned with the starting of processes
  • D. regulates the progress of job through various processes

  • Correct Answer
  • is concerned with the starting of processes 


  • Industrial Engineering and Production Management problems


    Search Results


    • 1. Work study involues

    • Options
    • A. only method study
    • B. only work measurement
    • C. method study and work measurement
    • D. only motion study
    • Discuss
    • 2. In CPM, the cost slope is determined by

    • Options
    • A.
    • B.
    • C.
    • D.
    • Discuss
    • 3. The main object of scientific layout is

    • Options
    • A. to produce better quality of product
    • B. to utilise maximum floor area
    • C. to minimise production delays
    • D. all of these
    • Discuss
    • 4. In big automobile repair shop, for elevating and moving the heavy parts such as complete engine assembly, gear box etc., an overhead crane and a fork lift truck is used.

    • Options
    • A. Yes
    • B. No
    • Discuss
    • 5. The aim of value engineering is to

    • Options
    • A. find the depreciation value of a machine
    • B. determine the selling price of a product
    • C. minimise the cost without change in quality of the product
    • D. all of the above
    • Discuss
    • 6. String diagram is used

    • Options
    • A. for checking the relative values of various layouts
    • B. when a group of workers are working at a place
    • C. where processes require the operator to be moved from one work place to another
    • D. all of the above
    • Discuss
    • 7. Which of the following are the guidelines for the construction of a network diagram?

    • Options
    • A. Each activity is represented by one and only one arrow in the network.
    • B. Dangling must be avoided in a network diagram.
    • C. Dummy activity consumes no time or resource.
    • D. all of the above
    • Discuss
    • 8. Gantt chart is used for

    • Options
    • A. inventory control
    • B. material handling
    • C. production schedule
    • D. machine repair schedules
    • Discuss
    • 9. In break even analysis, total cost consists of

    • Options
    • A. fixed cost + sales revenue
    • B. variable cost + sales revenue
    • C. fixed cost + variable cost
    • D. fixed cost + variable cost + profit
    • Discuss
    • 10. A-B-C analysis is used in

    • Options
    • A. CPM
    • B. PERT
    • C. inventory control
    • D. all of these
    • Discuss


    Comments

    There are no comments.

Enter a new Comment