logo

CuriousTab

CuriousTab

Discussion


Home Mechanical Engineering Industrial Engineering and Production Management Comments

  • Question
  • In big automobile repair shop, for elevating and moving the heavy parts such as complete engine assembly, gear box etc., an overhead crane and a fork lift truck is used.


  • Options
  • A. Yes
  • B. No

  • Correct Answer
  • Yes 


  • Industrial Engineering and Production Management problems


    Search Results


    • 1. The aim of value engineering is to

    • Options
    • A. find the depreciation value of a machine
    • B. determine the selling price of a product
    • C. minimise the cost without change in quality of the product
    • D. all of the above
    • Discuss
    • 2. Job evaluation is the method of determining the

    • Options
    • A. relative values of a job
    • B. worker's performance on a job
    • C. worth of the machine
    • D. value of overall production
    • Discuss
    • 3. The routing function in a production system design is concerned with

    • Options
    • A. manpower utilisation
    • B. quality assurance of the product
    • C. machine utilisation
    • D. optimising material flow through the plant
    • Discuss
    • 4. In inventory control theory, the economic order quantity is

    • Options
    • A. average level of inventory
    • B. optimum lot size
    • C. capacity of a warehouse
    • D. lot size corresponding to break-even analysis
    • Discuss
    • 5. A systematic job improvement sequence will consist of

    • Options
    • A. motion study
    • B. time study
    • C. job enrichment
    • D. all of these
    • Discuss
    • 6. The main object of scientific layout is

    • Options
    • A. to produce better quality of product
    • B. to utilise maximum floor area
    • C. to minimise production delays
    • D. all of these
    • Discuss
    • 7. In CPM, the cost slope is determined by

    • Options
    • A.
    • B.
    • C.
    • D.
    • Discuss
    • 8. Work study involues

    • Options
    • A. only method study
    • B. only work measurement
    • C. method study and work measurement
    • D. only motion study
    • Discuss
    • 9. Dispatching

    • Options
    • A. prescribes the sequence of operations to be followed
    • B. determines the programme for the operations
    • C. is concerned with the starting of processes
    • D. regulates the progress of job through various processes
    • Discuss
    • 10. String diagram is used

    • Options
    • A. for checking the relative values of various layouts
    • B. when a group of workers are working at a place
    • C. where processes require the operator to be moved from one work place to another
    • D. all of the above
    • Discuss


    Comments

    There are no comments.

Enter a new Comment