  • In a network shown in the below figure, the critical path is along
    In a network shown in the below figure, the critical path is along 1-2-3-4-8-9 1-2-3-5-6-7-8-9 1-2-3


  • Options
  • A. 1-2-3-4-8-9
  • B. 1-2-3-5-6-7-8-9
  • C. 1-2-3-4-7-8-9
  • D. 1-2-5-6-7-8-9

  • Correct Answer
  • 1-2-3-5-6-7-8-9 


  • Industrial Engineering and Production Management problems


    Search Results


    • 1. The determination of standard time in a complex job system is best done through

    • Options
    • A. stop watch time study
    • B. analysis of micromotions
    • C. grouping timing technique
    • D. analysis of standard data system
    • Discuss
    • 2. Production cost refers to prime cost plus

    • Options
    • A. factory overheads
    • B. factory and administration overheads
    • C. factory, administration and sales overheads
    • D. factory, administration, sales overheads and profit
    • Discuss
    • 3. The type of organisation preferred for a steel industry, is

    • Options
    • A. line organisation
    • B. functional organisation
    • C. line and staff organisation
    • D. line, staff and functional organisation
    • Discuss
    • 4. Queuing theory is associated with

    • Options
    • A. inventory
    • B. sales
    • C. waiting time
    • D. production time
    • Discuss
    • 5. Work sampling is applied for

    • Options
    • A. estimation of the percentage utilisation of machine tools
    • B. estimating the percentage of the time consumed by various job activities
    • C. finding out time standards, specially where the job is not repetitive and where time study by stop watch method is not possible
    • D. all of the above
    • Discuss
    • 6. Fixed position layout is also known as

    • Options
    • A. analytical layout
    • B. synthetic layout
    • C. static product layout
    • D. none of these
    • Discuss
    • 7. PERT is an event oriented technique.

    • Options
    • A. Correct
    • B. Incorrect
    • Discuss
    • 8. Line organisation is suitable for a big organisation.

    • Options
    • A. Correct
    • B. Incorrect
    • Discuss
    • 9. Direct expenses include

    • Options
    • A. factory expenses
    • B. selling expenses
    • C. administrative expenses
    • D. none of these
    • Discuss
    • 10. Probabilistic time for completion of any activity can be found out from

    • Options
    • A. optimistic time
    • B. pessimistic time
    • C. most likely time
    • D. all of these
    • Discuss


    Comments

    There are no comments.

Enter a new Comment