A's 2 day's work = | ❨ | 1 | x 2 | ❩ | = | 1 | . |
20 | 10 |
(A + B + C)'s 1 day's work = | ❨ | 1 | + | 1 | + | 1 | ❩ | = | 6 | = | 1 | . |
20 | 30 | 60 | 60 | 10 |
Work done in 3 days = | ❨ | 1 | + | 1 | ❩ | = | 1 | . |
10 | 10 | 5 |
Now, | 1 | work is done in 3 days. |
5 |
∴ Whole work will be done in (3 x 5) = 15 days.
(A + B)'s 1 day's work = | ❨ | 1 | + | 1 | ❩ | = | 1 | . |
15 | 10 | 6 |
Work done by A and B in 2 days = | ❨ | 1 | x 2 | ❩ | = | 1 | . |
6 | 3 |
Remaining work = | ❨ | 1 - | 1 | ❩ | = | 2 | . |
3 | 3 |
Now, | 1 | work is done by A in 1 day. |
15 |
∴ | 2 | work will be done by a in | ❨ | 15 x | 2 | ❩ | = 10 days. |
3 | 3 |
Hence, the total time taken = (10 + 2) = 12 days.
9 | 1 | days |
5 |
9 | 2 | days |
5 |
9 | 3 | days |
5 |
9 | 3 | days |
5 |
Explanation:
(A + B + C)'s 1 day's work = | 1 | , |
4 |
A's 1 day's work = | 1 | , |
16 |
B's 1 day's work = | 1 | . |
12 |
∴ C's 1 day's work = | 1 | - | ❨ | 1 | + | 1 | ❩ | = | ❨ | 1 | - | 7 | ❩ | = | 5 | . |
4 | 16 | 12 | 4 | 48 | 48 |
So, C alone can do the work in | 48 | = 9 | 3 | days. |
5 | 5 |
9 | 1 | days |
3 |
12 | 1 | days |
4 |
16 | 1 | days |
3 |
(A's 1 day's work) : (B's 1 day's work) = | 7 | : 1 = 7 : 4. |
4 |
Let A's and B's 1 day's work be 7x and 4x respectively.
Then, 7x + 4x = | 1 | ⟹ 11x = | 1 | ⟹ x = | 1 | . |
7 | 7 | 77 |
∴ A's 1 day's work = | ❨ | 1 | x 7 | ❩ | = | 1 | . |
77 | 11 |
13 | 1 | days |
3 |
13 | 1 | days |
3 |
Explanation:
Work done by X in 8 days = | ❨ | 1 | x 8 | ❩ | = | 1 | . |
40 | 5 |
Remaining work = | ❨ | 1 - | 1 | ❩ | = | 4 | . |
5 | 5 |
Now, | 4 | work is done by Y in 16 days. |
5 |
Whole work will be done by Y in | ❨ | 16 x | 5 | ❩ | = 20 days. |
4 |
∴ X's 1 day's work = | 1 | , Y's 1 day's work = | 1 | . |
40 | 20 |
(X + Y)'s 1 day's work = | ❨ | 1 | + | 1 | ❩ | = | 3 | . |
40 | 20 | 40 |
Hence, X and Y will together complete the work in | ❨ | 40 | ❩ | = 13 | 1 | days. |
3 | 3 |
Then, | x | - | x | = 2 |
10 | 15 |
⟹ 3x - 2x = 60
⟹ x = 60 km.
Time taken to travel 60 km at 10 km/hr = | ❨ | 60 | ❩hrs | = 6 hrs. |
10 |
So, Robert started 6 hours before 2 P.M. i.e., at 8 A.M.
∴ Required speed = | ❨ | 60 | ❩kmph. | = 12 kmph. |
5 |
2(A + B + C)'s 1 day's work = | ❨ | 1 | + | 1 | + | 1 | ❩ | = | 15 | = | 1 | . |
30 | 24 | 20 | 120 | 8 |
Therefore, (A + B + C)'s 1 day's work = | 1 | = | 1 | . |
2 x 8 | 16 |
Work done by A, B, C in 10 days = | 10 | = | 5 | . |
16 | 8 |
Remaining work = | ❨ | 1 - | 5 | ❩ | = | 3 | . |
8 | 8 |
A's 1 day's work = | ❨ | 1 | - | 1 | ❩ | = | 1 | . |
16 | 24 | 48 |
Now, | 1 | work is done by A in 1 day. |
48 |
So, | 3 | work will be done by A in | ❨ | 48 x | 3 | ❩ | = 18 days. |
8 | 8 |
Then, 4x + 6y = | 1 | and 3x + 7y = | 1 | . |
8 | 10 |
Solving the two equations, we get: x = | 11 | , y = | 1 |
400 | 400 |
∴ 1 woman's 1 day's work = | 1 | . |
400 |
⟹ 10 women's 1 day's work = | ❨ | 1 | x 10 | ❩ | = | 1 | . |
400 | 40 |
Hence, 10 women will complete the work in 40 days.
5 | 5 |
11 |
5 | 6 |
11 |
6 | 5 |
11 |
6 | 6 |
11 |
5 | 5 |
11 |
Q can complete the work in (8 x 10) hrs. = 80 hrs.
∴ P's1 hour's work = | 1 | and Q's 1 hour's work = | 1 | . |
96 | 80 |
(P + Q)'s 1 hour's work = | ❨ | 1 | + | 1 | ❩ | = | 11 | . |
96 | 80 | 480 |
So, both P and Q will finish the work in | ❨ | 480 | ❩ | hrs. |
11 |
∴ Number of days of 8 hours each = | ❨ | 480 | x | 1 | ❩ | = | 60 | days = 5 | 5 | days. |
11 | 8 | 11 | 11 |
Number of pages typed by Ravi in 1 hour = | 32 | = | 16 | . |
6 | 3 |
Number of pages typed by Kumar in 1 hour = | 40 | = 8. |
5 |
Number of pages typed by both in 1 hour = | ❨ | 16 | + 8 | ❩ | = | 40 | . |
3 | 3 |
∴ Time taken by both to type 110 pages = | ❨ | 110 x | 3 | ❩ | hours |
40 |
= 8 | 1 | hours (or) 8 hours 15 minutes. |
4 |
(A + B)'s 1 day's work = | 1 |
10 |
C's 1 day's work = | 1 |
50 |
(A + B + C)'s 1 day's work = | ❨ | 1 | + | 1 | ❩ | = | 6 | = | 3 | . .... (i) |
10 | 50 | 50 | 25 |
A's 1 day's work = (B + C)'s 1 day's work .... (ii)
From (i) and (ii), we get: 2 x (A's 1 day's work) = | 3 |
25 |
⟹ A's 1 day's work = | 3 | . |
50 |
∴ B's 1 day's work | ❨ | 1 | - | 3 | ❩ | = | 2 | = | 1 | . |
10 | 50 | 50 | 25 |
So, B alone could do the work in 25 days.
Comments
There are no comments.Copyright ©CuriousTab. All rights reserved.