Then, | x | - | x | = 2 |
10 | 15 |
⟹ 3x - 2x = 60
⟹ x = 60 km.
Time taken to travel 60 km at 10 km/hr = | ❨ | 60 | ❩hrs | = 6 hrs. |
10 |
So, Robert started 6 hours before 2 P.M. i.e., at 8 A.M.
∴ Required speed = | ❨ | 60 | ❩kmph. | = 12 kmph. |
5 |
36 | 2 |
3 |
37 | 1 |
2 |
Then, | x | - | x | = | 40 | ⟹ 2y(y + 3) = 9x ....(i) |
y | y + 3 | 60 |
And, | x | - | x | = | 40 | ⟹ y(y - 2) = 3x ....(ii) |
y -2 | y | 60 |
On dividing (i) by (ii), we get: x = 40.
Then, | 120 | + | 480 | = 8 ⟹ | 1 | + | 4 | = | 1 | ....(i) |
x | y | x | y | 15 |
And, | 200 | + | 400 | = | 25 | ⟹ | 1 | + | 2 | = | 1 | ....(ii) |
x | y | 3 | x | y | 24 |
Solving (i) and (ii), we get: x = 60 and y = 80.
∴ Ratio of speeds = 60 : 80 = 3 : 4.
Then, | 30 | - | 30 | = 3 |
x | 2x |
⟹ 6x = 30
⟹ x = 5 km/hr.
Time taken to cover 9 km = | ❨ | 9 | x 60 | ❩min | = 10 min. |
54 |
Total time taken = | ❨ | 160 | + | 160 | ❩hrs. | = | 9 | hrs. |
64 | 80 | 2 |
∴ Average speed = | ❨ | 320 x | 2 | ❩km/hr | = 71.11 km/hr. |
9 |
13 | 1 | days |
3 |
13 | 1 | days |
3 |
Explanation:
Work done by X in 8 days = | ❨ | 1 | x 8 | ❩ | = | 1 | . |
40 | 5 |
Remaining work = | ❨ | 1 - | 1 | ❩ | = | 4 | . |
5 | 5 |
Now, | 4 | work is done by Y in 16 days. |
5 |
Whole work will be done by Y in | ❨ | 16 x | 5 | ❩ | = 20 days. |
4 |
∴ X's 1 day's work = | 1 | , Y's 1 day's work = | 1 | . |
40 | 20 |
(X + Y)'s 1 day's work = | ❨ | 1 | + | 1 | ❩ | = | 3 | . |
40 | 20 | 40 |
Hence, X and Y will together complete the work in | ❨ | 40 | ❩ | = 13 | 1 | days. |
3 | 3 |
9 | 1 | days |
3 |
12 | 1 | days |
4 |
16 | 1 | days |
3 |
(A's 1 day's work) : (B's 1 day's work) = | 7 | : 1 = 7 : 4. |
4 |
Let A's and B's 1 day's work be 7x and 4x respectively.
Then, 7x + 4x = | 1 | ⟹ 11x = | 1 | ⟹ x = | 1 | . |
7 | 7 | 77 |
∴ A's 1 day's work = | ❨ | 1 | x 7 | ❩ | = | 1 | . |
77 | 11 |
9 | 1 | days |
5 |
9 | 2 | days |
5 |
9 | 3 | days |
5 |
9 | 3 | days |
5 |
Explanation:
(A + B + C)'s 1 day's work = | 1 | , |
4 |
A's 1 day's work = | 1 | , |
16 |
B's 1 day's work = | 1 | . |
12 |
∴ C's 1 day's work = | 1 | - | ❨ | 1 | + | 1 | ❩ | = | ❨ | 1 | - | 7 | ❩ | = | 5 | . |
4 | 16 | 12 | 4 | 48 | 48 |
So, C alone can do the work in | 48 | = 9 | 3 | days. |
5 | 5 |
(A + B)'s 1 day's work = | ❨ | 1 | + | 1 | ❩ | = | 1 | . |
15 | 10 | 6 |
Work done by A and B in 2 days = | ❨ | 1 | x 2 | ❩ | = | 1 | . |
6 | 3 |
Remaining work = | ❨ | 1 - | 1 | ❩ | = | 2 | . |
3 | 3 |
Now, | 1 | work is done by A in 1 day. |
15 |
∴ | 2 | work will be done by a in | ❨ | 15 x | 2 | ❩ | = 10 days. |
3 | 3 |
Hence, the total time taken = (10 + 2) = 12 days.
A's 2 day's work = | ❨ | 1 | x 2 | ❩ | = | 1 | . |
20 | 10 |
(A + B + C)'s 1 day's work = | ❨ | 1 | + | 1 | + | 1 | ❩ | = | 6 | = | 1 | . |
20 | 30 | 60 | 60 | 10 |
Work done in 3 days = | ❨ | 1 | + | 1 | ❩ | = | 1 | . |
10 | 10 | 5 |
Now, | 1 | work is done in 3 days. |
5 |
∴ Whole work will be done in (3 x 5) = 15 days.
Comments
There are no comments.Copyright ©CuriousTab. All rights reserved.