  • Manjeet can do a work in 18 hours. If he is joined by Jaya who is 100% more efficient, in what time will they together finish the work?


  • Options
  • A. 6 hours
  • B. 3 hours
  • C. 12 hours
  • D. 24 hours

  • Correct Answer
  • 6 hours 

  • Tags: Bank Exams

    Time and Work problems


    Search Results


    • 1. A can paint a house in 45 days and B can do it in 15 days. Along with C, they did the job in 5 days only. Then, C alone can do the job in how many days?

    • Options
    • A. 12
    • B. 9
    • C. 15
    • D. 8
    • Discuss
    • 2. A can do a work in 16 days and B in 20 days. If they work on it together for 8 days, then what fraction of work is left?

    • Options
    • A. 1/3
    • B. 1/6
    • C. 2/9
    • D. 1/10
    • Discuss
    • 3. A is thrice as productive as C. Together they can complete a job in 22.5 days. If B joins them after they have worked for 15 days then in how many days can they finish the rest of the job if B alone can do the job in 15 days?

    • Options
    • A. 6
    • B. 3
    • C. 9
    • D. 2
    • Discuss
    • 4. Working together A, B and C can complete a task in 12 days. A and B can do the task in 55 days and 66 days respectively if they worked alone. In how many days can C do the task if he worked alone?

    • Options
    • A. 22
    • B. 44
    • C. 20
    • D. 40
    • Discuss
    • 5. If A had worked alone he would have taken 63 hours to do the task. What is B's share, if A and B work together on a task finishing it in 36 hours and they get paid Rs 5,950 for it?

    • Options
    • A. 3400
    • B. 3600
    • C. 2550
    • D. 2750
    • Discuss
    • 6. Some carpenters promised to do a job in 15 days but 3 of them were absent and remaining did the job in 20 days. What was the original number of carpenters?

    • Options
    • A. 10
    • B. 15
    • C. 12
    • D. 14
    • Discuss
    • 7. P and Q can do a project in 150 and 100 days respectively. In how many days can they complete 60% of the project if they work together?

    • Options
    • A. 12 days
    • B. 72 days
    • C. 42 days
    • D. 36 days
    • Discuss
    • 8. Azhar is 4 times as good a workman as Balaraj and therefore is able to finish a job in 45 days less than Balaraj. Working together, they can do it in:

    • Options
    • A. 6 days
    • B. 18 days
    • C. 24 days
    • D. 12 days
    • Discuss
    • 9. Sister can bake 50 cakes in 25 hours, Sister and Mummy together can bake 75 cakes in 15 hours. How many cakes Mummy can bake in 15 hours?

    • Options
    • A. 25
    • B. 45
    • C. 20
    • D. 10
    • Discuss
    • 10. A does 50% of a work in 12 days. He then calls in B and they together finish the remaining work in 8 days. How long B alone would take to complete the whole work?

    • Options
    • A. 12 days
    • B. 24 days
    • C. 36 days
    • D. 48 days
    • Discuss