Home Aptitude Time and Work Comments

  • Question
  • A and B can together do a piece of work in 6 days and A alone can do it in 9 days. The number of days B will take to do it alone is


  • Options
  • A. 18 days
  • B. 24 days
  • C. 9 days
  • D. 12 days

  • Correct Answer
  • 18 days 

  • Tags: Bank Exams

    Time and Work problems


    Search Results


    • 1. A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in

    • Options
    • A. 16 days
    • B. 24 days
    • C. 28 days
    • D. 29 days
    • Discuss
    • 2. A,B and C contract a work for Rs. 440. Together A and B are to do 9/11 of the work. The share of C should be:

    • Options
    • A. 75
    • B. 90
    • C. 100
    • D. 80
    • Discuss
    • 3. X, Y and Z can do a piece of work in 30, 40 and 50 days respectively. All three of them began the work together but Y left 4 days before completion of the work. In how many days was the work completed?

    • Options
    • A. 660/47
    • B. 640/47
    • C. 680/47
    • D. 665/47
    • Discuss
    • 4. A and B together do a job in 15 days and A alone could do the same job in 20 days. How many days would B take to do half the job if he worked alone?

    • Options
    • A. 60
    • B. 30
    • C. 45
    • D. 40
    • Discuss
    • 5. A can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. C can alone do the work in

    • Options
    • A. 5 days
    • B. 6 days
    • C. 10 days
    • D. 12 days
    • Discuss
    • 6. A is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is

    • Options
    • A. 20 days
    • B. 21 days
    • C. 22 days
    • D. 24 days
    • Discuss
    • 7. The rate of working of A and B are in the ratio of 2:3. The number of days taken by them to finish the work is in the ratio:

    • Options
    • A. 2:3
    • B. 4:9
    • C. 3:2
    • D. 9:4
    • Discuss
    • 8. A and B undertake a piece of work for Rs. 250 . A alone can do that work in 5 days and B alone can do that work in 15 days . With the help of C, they finish the work in 3 days . If every one gets paid in proportion to work done by them, the amount C will get is

    • Options
    • A. Rs.50
    • B. Rs.100
    • C. Rs.150
    • D. Rs.200
    • Discuss
    • 9. A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days will A, B and C finish it, working all together?

    • Options
    • A. 6 days
    • B. 5 1/4 days
    • C. 4 4/11 days
    • D. 4 days
    • Discuss
    • 10. If A and B together do a job in 7.5 days and if A could do the job in 10 days if he worked alone. How many days would B take to do the job if he worked alone?

    • Options
    • A. 30
    • B. 40
    • C. 25
    • D. 50
    • Discuss


    Comments

    There are no comments.

Enter a new Comment