  • Question
  • A can do a work in 24 days. B is 20% more efficient than A. If C can do the work in 10 more days than B, find the time taken by A and C together to complete the work.


  • Options
  • A. 43/3 days
  • B. 40/3 days
  • C. 50/3 days
  • D. 41/2 days

  • Correct Answer
  • 40/3 days 

    Explanation

    A takes 24 days to complete a work.
    B is 20% more efficient than A,
    hence B will take (24*100)/120 = 20 days.
    C takes (20+10) = 30 days.
    Time taken by A & C in completing the work = (24*30)/(24+30) = (24*30)/54 = 40/3 days.

  • Tags: Bank Exams

    Time and Work problems


    Search Results


    • 1. Type 1 workers can do three times the work of Type 2 workers. Twelve Type 1 workers can complete a task in 10 days. How many days would it have taken 4 Type 1 and 8 Type 2 workers to complete the same task?

    • Options
    • A. 16
    • B. 17
    • C. 20
    • D. 18
    • Discuss
    • 2. A is 50% more efficient than B. They together start the work and 7/12th of work is left after 8 days. Find in what time B alone will complete the whole work.

    • Options
    • A. 36 days
    • B. 44 days
    • C. 50 days
    • D. 40 days
    • Discuss
    • 3. A alone can do a work in 20 days. B is 125% more efficient than A. A and B started working and worked for 4 days. If C alone completed the remaining job in 22 days. How many days C alone takes to complete the entire job?

    • Options
    • A. 30
    • B. 35
    • C. 40
    • D. 42
    • Discuss
    • 4. If two flood gates A and B function simultaneously, the reservoir will be filled iu 6 hours. Gate A fills the reservoir 5 hours faster than gate B. How many hours does the faster flood gate take to fill the reservoir?

    • Options
    • A. 7 hrs
    • B. 13 hrs
    • C. 5 hrs
    • D. 10 hrs
    • Discuss
    • 5. X can complete a task in 8 days, whereas Y can complete the same task in 10 days. If they work together, in how many days will the task be completed?

    • Options
    • A. 40/9
    • B. 9/40
    • C. 44/9
    • D. 9/44
    • Discuss
    • 6. Prabhat has done 1/2 of a job in 12 days. Santosh completes the rest of the job in 6 days. In how many days can they together do the job?

    • Options
    • A. 12 days
    • B. 4 days
    • C. 8 days
    • D. 16 days
    • Discuss
    • 7. A takes 24 day in completing a work alone. Time taken by A in completing 1/3rd of the work is equal to the time taken by B in completing half of the work. How many days will be taken in completing the work if both A & B start working together?

    • Options
    • A. 21/3 days
    • B. 48 days
    • C. 40 days
    • D. 48/5 days
    • Discuss
    • 8. 48 people could complete a task in 17 days. After 6 days, 4 of the workers left. How many days from then will it take to complete the task?

    • Options
    • A. 12
    • B. 13
    • C. 15
    • D. 16
    • Discuss
    • 9. Two typists of varying skills can do a typing jobin6 minutesifthey work together.Ifthe first typist typed alone for 4 minutes and then the second typist typed alone for 6 minutes, they would be left with 1/5 of the whole work.Howmany minutes would it take the slower typist to complete the typing job working alone?

    • Options
    • A. 10 minutes
    • B. 15 minutes
    • C. 12 minutes
    • D. 20 minutes
    • Discuss
    • 10. X can do a piece of work in 'p' days and Y can do the same work in 'q' days . Then the number of days in which X and Y can together do that work is

    • Options
    • A. p+q2
    • B. 1p+1q
    • C. pqp+q
    • D. Pq
    • Discuss


    Comments

    There are no comments.

Enter a new Comment