A completed their work in 8 X 2 = 16 days
B completed their work in 8 X 3 = 24 days
A and B one day work1/16 + 1/245/48
A and B completed their work in 48/5 days = 9.6 days
(1/24 + 1/30) x 6 + (1/24 + 1/C) x 11 = 1
Time required will be in ratio = 5:4
B alone will do it in =16 days