Home Aptitude Time and Work Comments

  • Question
  • Twenty women can do a work in sixteen days. Sixteen men can complete the same work in fifteen days. The ratio between the capacity of a man and a woman is


  • Options
  • A. 3:4
  • B. 4:3
  • C. 5:3
  • D. 5:7

  • Correct Answer
  • 4:3 

  • Tags: Bank Exams

    Time and Work problems


    Search Results


    • 1. Mehdi can complete a work in 25 hours. If he is joined by Jahnavi who is 50% more efficient, in what time will they together finish the work?

    • Options
    • A. 12 hours
    • B. 10 hours
    • C. 3 hours
    • D. 9 hours
    • Discuss
    • 2. A does 75% of a work in 50 days. He then calls in B and they together finish the remaining work in 10 days. How long B alone would take to complete the whole work?

    • Options
    • A. 200 days
    • B. 50 days
    • C. 100 days
    • D. 125 days
    • Discuss
    • 3. A man starts moving from a place A and reaches the place B in 26 hours. He covers 1/3rd of the distance at the speed of 4 km/hr and covers the remaining distance at the speed of 5 km/hr. What is the distance (in km) between A and B?

    • Options
    • A. 45
    • B. 80
    • C. 120
    • D. 90
    • Discuss
    • 4. A work can be completed by 28 women in 36 days. If 4 women leave after working for 18 days, then how many days will be needed to complete the remaining work?

    • Options
    • A. 24
    • B. 21
    • C. 27
    • D. 25
    • Discuss
    • 5. Akash is 3 times as good a workman as Baldev and therefore is able to finish a job in 40 days less than Baldev. Working together, they can finish it in _____.

    • Options
    • A. 15 days
    • B. 60 days
    • C. 20 days
    • D. 10 days
    • Discuss
    • 6. A mason can build a wall in 70 hours. After 7 hours he takes a break. What fraction of the wall is yet to be built?

    • Options
    • A. 0.9
    • B. 0.8
    • C. 0.5
    • D. 0.75
    • Discuss
    • 7. A can paint a house in 42 days and B can do it in 21 days. Along with C, they can finish the job in 7 days only.C alone can do the painting job in how many days, ?

    • Options
    • A. 9
    • B. 12
    • C. 14
    • D. 15
    • Discuss
    • 8. Sashi can do a piece of work in 20 days. Tanya is 25% more efficient than Sashi. The number of days taken by Tanya to do the same piece of work is:

    • Options
    • A. 15
    • B. 16
    • C. 18
    • D. 25
    • Discuss
    • 9. 18 men or 36 boys working 6 hours a day can plough a field in 24 days. In how many days will 24 men and 24 boys working 9 hours a day plough the same field ?

    • Options
    • A. 9
    • B. 10
    • C. 6
    • D. 8
    • Discuss
    • 10. Anil is twice as good as workman as Bimal and together they finish a piece of work in 9 days. In how many days will Anil alone finish the work?

    • Options
    • A. 12.5
    • B. 11.5
    • C. 10.5
    • D. 13.5
    • Discuss