X, Y and Z can do a piece of work in 30,40 and 50 days respectively. All three of them began the work together but Y left 4 days before completion of the work. In how many days was the work completed?
1. A and B together do a job in 12 days and A could do the job in 20 days if he worked alone. How many days would B take to do the job if he worked alone?
3. A can make a cupboard in 10 days and B can do it in 50 days. Along with C, they did the job in 6.25 days only. Then in how many days C alone can do the job?
4. Tushar takes 6 hours to complete a piece of work, while Amar completes the same work in 10 hours. If both of them work together, then what is the time required to complete the work?
5. A and B do (3/5) th part of a work and the rest of the work is completed by C. If A, B and C take the same work for Rs 5000, then what is the share of C (in Rs)?
6. P, Q and R together can make a table in 40 minutes. P and Q together can make it in 60 minutes. How much time (in minutes) will R alone take to make the table?
8. Akash is 3 times as good a workman as Baldev and therefore is able to finish a job in 40 days less than Baldev. Working together, they can finish it in _____.
9. A work can be completed by 28 women in 36 days. If 4 women leave after working for 18 days, then how many days will be needed to complete the remaining work?
10. A man starts moving from a place A and reaches the place B in 26 hours. He covers 1/3rd of the distance at the speed of 4 km/hr and covers the remaining distance at the speed of 5 km/hr. What is the distance (in km) between A and B?