Lcm of 25 and 20 is 100. So total work = 100 units
Ranjith can do 4 units per day while anju can do 5 units per day
They together complete 5 days of work i.e 9 x 5 = 45 units
The remaining 55 units of work is done by anju in 55/5 days (or) 11 days