Let M, N and O worked together for x days.
From the given data,
M alone worked for 8 days
M,N,O worked for x days
N, O worked for 1 day
But given that
M alone can complete the work in 18 days
N alone can complete the work in 36 days
O alone can complete the work in 54 days
The total work can be the LCM of 18, 6, 54 = 108 units
M's 1 day work = 108/18 = 6 units
N's 1 day work = 108/36 = 3 units
O's 1 day work = 108/54 = 2 units
Now, the equation is
8 x 6 + 11x + 5 x 1 = 108
48 + 11x + 5 = 108
11x = 103 - 48
11x = 55
x = 5 days.
Hence, all M,N and O together worked for 5 days.
We have the important relation, More work, More time (days)
? A piece of work can be done in 6 days.
? Three times of work of same type can be done in 6 x 3
= 18 days
? = 750.0003 ÷ 19.999
? ? ? 750 ÷ 20
? ? ? 375 ? 38
Subtract 20, 25, 30, 35, 40, 45 from successive numbers. So 0 is wrong.
NA
Each previous number is multiplied by 2.
? 8 m shadow means original height = 12 m
? 1 m shadow means original height = 12/8 m
? 100 m shadow means original height = (12/8) x 100 m
= (6/4) x 100 = 6 x 25 = 150 m
Let 8% of 96 = y of 1/25
? (8 x 96)/100 = y/25
? y = (8 x 96 x 25)/100 = 192
Since the principal is not given, so data is inadequate.
Comments
There are no comments.Copyright ©CuriousTab. All rights reserved.