  • Question
  • It takes one minute to fill 2/7 th of a vessel. What is the time taken in minutes to fill the whole of the vessel ?


  • Options
  • A. 1/7 min
  • B. 7/2 min
  • C. 5/7 min
  • D. 7/5 min

  • Correct Answer
  • 7/2 min 

    Explanation

    Time taken to fill 2/7 = 1
    Then to fill full 1 = ?
    ? = 1/(2/7) = 7/2 minutes.

  • Tags: AIEEE, Bank Exams, CAT, GATE, Bank Clerk, Bank PO

    Time and Work problems


    Search Results


    • 1. A can do a piece of work in 15 days and B can do it in 16 days and C can do it 24 days. They started the work together and A leaves after 3 days and B leaves after 4 days from the beginning. How long will work lost ?

    • Options
    • A. 10 2/3 days
    • B. 13 1/5 days
    • C. 12 2/3 days
    • D. 11 5/7 days
    • Discuss
    • 2. A can complete a piece of work in 12 days and B is 60% more efficient than A. In how many days B will complete the same work ?

    • Options
    • A. 8.7 hrs
    • B. 5.2 hrs
    • C. 5 hrs
    • D. 7.5 hrs
    • Discuss
    • 3. There is sufficient salary to give K for 10 days and L for 15 days. Then how many days will the money last if both has to be given the salary ?

    • Options
    • A. 6 days
    • B. 12 days
    • C. 4 days
    • D. 9 days
    • Discuss
    • 4. In a regular week, there are 5 working days and for each day, the working hours are 8. A man gets Rs. 2.40 per hour for regular work and Rs. 3.20 per hours for overtime. If he earns Rs. 432 in 4 weeks, then how many hours does he work for ?

    • Options
    • A. 145
    • B. 165
    • C. 175
    • D. 135
    • Discuss
    • 5. A is 3 times faster than B. If A can finish a work 32 days less than that of B, find the number of days need to finish the work if both are working together?

    • Options
    • A. 12 days
    • B. 24 days
    • C. 32 days
    • D. 16 days
    • Discuss
    • 6. M, N and O can complete the work in 18, 36 and 54 days respectively. M started the work and worked for 8 days, then N and O joined him and they all worked together for some days. M left the job one day before completion of work. For how many days they all worked together?

    • Options
    • A. 4
    • B. 5
    • C. 3
    • D. 6
    • Discuss
    • 7. 70000 a year is how much an hour?

    • Options
    • A. 80
    • B. 8
    • C. 0.8
    • D. 0.08
    • Discuss
    • 8. A and B can complete a task in 1.5 days. However, A had to leave a few days before the task wascompleted and hence it took 2 days in all to complete the task. If A alone could complete the work in2.625 days, how many days before the work getting over did A leave?

    • Options
    • A. 1.125
    • B. 0.625
    • C. 0.375
    • D. 0.875
    • Discuss
    • 9. A can do a certain job in 12 days. B is 60% more efficient than A. Then B can do the same piece of work in

    • Options
    • A. 8 days
    • B. 7.5 days
    • C. 6.4 days
    • D. 5.5 days
    • Discuss
    • 10. 2 men or 3 women can complete a job in 96 days. Then 6 men and 7 women will complete the same job in how many days?

    • Options
    • A. 18
    • B. 27
    • C. 20
    • D. 24
    • Discuss


    Comments

    There are no comments.

Enter a new Comment