  • A is 3 times faster than B. If A can finish a work 32 days less than that of B, find the number of days need to finish the work if both are working together?


  • Options
  • A. 12 days
  • B. 24 days
  • C. 32 days
  • D. 16 days

  • Correct Answer
  • 12 days 

    Explanation

    It is given that efficiency ratio =3:1

    so time ratio will be 1:3 (since work is same)

     

    Also given that time diff = 32 days. ratio difference = 3-1 =2 

    2 ratio = 32 days

    1 ratio = 16 days.

    So A will alone finish it in 16 days and B will finish it in 16*3 = 48 days.

     

    Total work = LCM of 16 and 48 = 48.

    Total time = Total work/Total efficiency 

    ie; 48/4= 12 days.

  • Tags: Bank Exams, Bank PO, Bank Clerk

    Time and Work problems


    Search Results


    • 1. K, L and M can do a piece of work in 20, 30 and 60 days respectively. In how many days can K do the total work if he is assisted by L and M on every third day ?

    • Options
    • A. 15 days
    • B. 13 days
    • C. 12 days
    • D. 10 days
    • Discuss
    • 2. K is 4 times as fast as L and working together, they can complete a work in 24 days. In how many days can L alone complete the work ?

    • Options
    • A. 30 days
    • B. 40 days
    • C. 120 days
    • D. 80 days
    • Discuss
    • 3. B would have taken 10 hours more than what A would have taken to complete a task if each of them worked alone. Working together they can complete the task in 12 hours. How many hours would B take to do 50% of the task?

    • Options
    • A. 30
    • B. 15
    • C. 20
    • D. 10
    • Discuss
    • 4. 10 women can do a piece of work in 6 days, 6 men can do same work in 5 days and 8 children can do it in 10 days. What is the ratio of the efficiency of a woman, a man and a child respectively?

    • Options
    • A. 4 : 6 : 3
    • B. 4 : 5 : 3
    • C. 2 : 4 : 3
    • D. 4 : 8 : 3
    • Discuss
    • 5. Raman can do a work in 5 days, Jatin can do the same work in 7 days and Sachin can do the same work in 9 days. If they do the same work together and they are paid Rs 2860, then what is the share (in Rs) of Raman?

    • Options
    • A. 1260
    • B. 700
    • C. 900
    • D. 870
    • Discuss
    • 6. In a regular week, there are 5 working days and for each day, the working hours are 8. A man gets Rs. 2.40 per hour for regular work and Rs. 3.20 per hours for overtime. If he earns Rs. 432 in 4 weeks, then how many hours does he work for ?

    • Options
    • A. 145
    • B. 165
    • C. 175
    • D. 135
    • Discuss
    • 7. There is sufficient salary to give K for 10 days and L for 15 days. Then how many days will the money last if both has to be given the salary ?

    • Options
    • A. 6 days
    • B. 12 days
    • C. 4 days
    • D. 9 days
    • Discuss
    • 8. A can complete a piece of work in 12 days and B is 60% more efficient than A. In how many days B will complete the same work ?

    • Options
    • A. 8.7 hrs
    • B. 5.2 hrs
    • C. 5 hrs
    • D. 7.5 hrs
    • Discuss
    • 9. A can do a piece of work in 15 days and B can do it in 16 days and C can do it 24 days. They started the work together and A leaves after 3 days and B leaves after 4 days from the beginning. How long will work lost ?

    • Options
    • A. 10 2/3 days
    • B. 13 1/5 days
    • C. 12 2/3 days
    • D. 11 5/7 days
    • Discuss
    • 10. It takes one minute to fill 2/7 th of a vessel. What is the time taken in minutes to fill the whole of the vessel ?

    • Options
    • A. 1/7 min
    • B. 7/2 min
    • C. 5/7 min
    • D. 7/5 min
    • Discuss


    Comments

    There are no comments.

Enter a new Comment